    INTRODUCTION.

    The section of the Pennsylvania Railroad Tunnel work described in this paper is that lying between Tenth Avenue, New York City, and the large shaft built by the Company at Weehawken, N. J., and thus comprises the crossing of the North or Hudson River, the barrier which has stood for such a long time between the railroads and their possession of terminal stations in New York City. The general plan and section, Plate XXVIII, shows the work included.

    This paper is written from the point of view of those engaged by the Chief Engineer of the Railroad Company to look after the work of construction in the field. The history of the undertaking is not included, the various phases through which many of the designs and plans passed are not followed, nor are the considerations regarding foundations under the subaqueous portions of the tunnels and the various tests made in connection with this subject set out, as all these matters will be found in other papers on these tunnels.

    This paper only aims to describe, as briefly as possible, the actual designs which were finally adopted, the actual conditions met on the ground, and the methods of construction adopted by the contractors.

    For easy reference, and to keep the descriptions of work of a similar character together, the subject will be treated under the four main headings, viz.: Shafts, Plant, Land Tunnels, and River Tunnels.

    SHAFTS.

    It is not intended to give much length to the description of the Shafts or the Land Tunnels, as more interest will probably center in the River Tunnels.

    The shafts did not form part of the regular tunnel contract, but were built under contract by the United Engineering and Contracting Company while the contract plans for the tunnel were being prepared. In this way, when the tunnel contracts were let, the contractor found the shafts ready, and he could get at his work at once.

    Two shafts were provided, one on the New York side and one on the New Jersey side. Their exact situation is shown on Plate XXVIII. They were placed as near as possible to the point at which the disappearance of the rock from the tunnels made it necessary to start the shield-driven portion of the work.

    The details of the shafts will now be described briefly.

    The Manhattan Shaft.--The Manhattan Shaft is located about 100 ft. north of the tunnel center; there was nothing noticeable about its construction. General figures relating to both shafts are given in Table 1.

    The Weehawken Shaft.--The Weehawken Shaft is shown in Fig. 1. This, as will be seen from Table 1, was a comparatively large piece of work. The shaft is over the tunnels, and includes both of them. In the original design the wall of the shaft was intended to follow in plan the property line shown in Fig. 2, and merely to extend down to the surface of the rock, which, as disclosed by the preliminary borings, was here about 15 ft. below the surface.

    However, as the excavation proceeded, it was found that this plan would not do, as the depth to the rock surface varied greatly, and was often much lower than expected; the rock itself, moreover, was very treacherous, the cause being that the line of junction between the triassic sandstone, which is here the country rock, and the intrusive trap of the Bergen Hill ridge, occurs about one-third of the length of the shaft from its western end, causing more or less disintegration of both kinds of rock.

    Therefore it was decided to line the shaft with concrete throughout its entire depth, the shape being changed to a rectangular plan, as shown in the drawings. At the same time that the shaft was excavated, a length of 40 ft. of tunnels at each end of it was taken out, also on account of the treacherous nature of the ground, thus avoiding risk of injury to the shaft when the tunnel contractors commenced work.

    There was much trouble with floods during the fall of 1903, and numerous heavy falls of ground occurred, in spite of extreme care and much heavy timbering. The greatest care was also taken in placing the concrete lining, and the framing to support the forms was carefully designed and of heavy construction; the forms were of first-class workmanship, and great care was taken to keep them true to line.

    A smooth surface was given to the concrete by placing a 3-in. layer of mortar at the front of the walls and tamping this dry facing mixture well down with the rest of the concrete. The east and west walls act as retaining walls, while those on the north and south are facing walls, and are tied to the rock with steel rods embedded and grouted into the rock and into the concrete.

    Ample drainage for water at the back of the wall was provided by upright, open-joint, vitrified drains at frequent intervals, with dry-laid stone drains leading to them from all wet spots in the ground. A general view of the finished work is shown in Fig. 1, Plate XXIX, and Table 1 gives the most important dates and figures relating to this shaft.

    TABLE 1.--PARTICULARS OF SHAFTS ON THE NORTH RIVER TUNNELS OF THE

    PENNSYLVANIA RAILROAD TUNNELS INTO NEW YORK CITY.

    +===========+=====+======+======+==========+========+===========+========+ |Location. |Depth| Width|Length|Excavation|Concrete| Date| Date| | | in| in| in|(including|in cubic|commenced.|finished.| | |feet.| feet.| feet.| drifts),| yards.| | | | | | | | in cubic| | | | | | | | | yards. | | | | +-----------+-----+------+------+----------+--------+----------+---------+ |Manhattan: | 55| 22| 32| 2,010| 209|June 10th,| December| |11th Avenue| | | | | | 1903.| 11th,| |and 32d | | | | | | | 1903.| |Street. | | | | | | | | | | | | | | | | | |Weehawken: | 76| At| At| 55,315| 9,810|June 11th,|September| |Baldwin | |bottom|bottom| | | 1903.|1st, | |Avenue. | |56, at|115.75| | | |1904. | | | | top|at top| | | | | | | | 100.| 154.| | | | | |===========+=====+======+======+==========+========+==========+=========+

    +==========+====================+=============+============+===========+ |Location. |Ground met: |Lined with: | Cost to | Cost per | | | | | Railroad |cubic foot.| | | | | Company. | | +----------+--------------------+-------------+------------+-----------+ |Manhattan:|Top 13 ft. filled; |Concrete | $12,943.75 | $0.335 | |11th |red mica schist and |reinforced | | | |Avenue and|granite. |with steel | | | |32d | |beams down to| | | |Street. | |rock. | | | | | | | | | |Weehawken:|Top 6 ft. filled, 30|Concrete with| 166,162,98 | 0.337 | |Baldwin |ft. sand and |steel | | | |Avenue. |hardpan, decomposed |tie-rods in | | | | |rock (trap and |rock. | | | | |sandstone) below. | | | | +==========+====================+=============+============+===========+

    [Illustration: FINAL DESIGN OF WEEHAWKEN SHAFT PLAN LONGITUDINAL SECTION TRANSVERSE SECTION FIG. 1.]

    After the tunnel work was finished, both shafts were provided with stairs leading to the surface, a protective head-house was placed over the New York Shaft, and a reinforced concrete fence, 8 ft. high, was built around the Weehawken Shaft on the Company's property line, that is, following the outline of the shaft as originally designed.

    PLANT.

    Working Sites.

    Before beginning a description of the tunnel work, it may be well to set out in some detail the arrangements made on the surface for conducting the work underground.

    All the work was carried on from two shafts, one at Eleventh Avenue and 32d Street, New York City--called the Manhattan Shaft--and one at Baldwin Avenue, Weehawken, N. J.--called the Weehawken Shaft.

    [Illustration: WEEHAWKEN SHAFT. EXCAVATION FIG. 2.]

    The characteristics of the two sites were radically different, and called for different methods of handling the transportation problem. The shaft site at Manhattan is shown on Plate XXX. It will be seen that there was not much room, in fact, the site was too cramped for comfort; the total area, including the space occupied by the old foundry, used for power-houses, offices, etc., was about 3,250 sq. yd.

    This made it necessary to have two stages, one on the ground level for handling materials into the yard, and an overhead gantry on which the excavated materials were handled off the premises. The yard at Weehawken was much larger; it is also shown on Plate XXX. Its area was about 15,400 sq. yd. in the yard proper, and there was an additional space of about 750 sq. yd. alongside the wharf at the "North Slip," on the river front, connected with the main portion of the yard by an overhead trestle.

    All the cars at Manhattan were moved by hand, but at Weehawken two electric locomotives with overhead transmission were used.

    Power-House Plant.

    At the Manhattan Shaft the power-house plant was installed on the ground floor of the old foundry building which occupied the north side of the leased area. This was a brick building, quite old, and in rather a tumble-down condition when the Company took possession, and in consequence it required quite a good deal of repair and strengthening work. The first floor of the building was used by the contractor as offices, men's quarters, doctor's offices, and so on, and on the next one above, which was the top floor, were the offices occupied by the Railroad Company's field engineering staff.

    On the Weehawken side, the plant was housed in a wooden-frame, single-story structure, covered with corrugated iron. It was rectangular in plan, measuring 80 by 130 ft.

    At both sides of the river the engines were bedded on solid concrete on a rock foundation.

    The installation of the plant on the Manhattan side occupied from May, 1904, to April, 1905, and on the Weehawken side from September, 1904, to April, 1905. Air pressure was on the tunnels at the New York side on June 25th, 1905, and on the Weehawken side on the 29th of the same month.

    [Illustration: PLATE XXIX. TRANS. AM. SOC. CIV. ENGRS. VOL. LXVIII, No.

    1155. HEWETT AND BROWN ON PENNSYLVANIA R. R. TUNNELS: NORTH RIVER

    TUNNELS. FIG. 1. FIG. 2.]

    The plants contained in the two power-houses were almost identical, there being only slight differences in the details of arrangement due to local conditions. A list of the main items of the plant at one power-house is shown in Table 2.

    TABLE 2.--PLANT AT ONE POWER-HOUSE.

    +======+======================================================+========+ |No. of| | | |items.|Description of item. | Cost.| |------+------------------------------------------------------+--------| |Three |500-h.p. water-tube Sterling boilers | $15,186| |Two |Feed pumps, George F. Blake Manufacturing Company | 740| |One |Henry R.

    Worthington surface condenser | 6,539| |Two |Electrically-driven circulating pumps on river front | 5,961| |Three |Low-pressure compressors, Ingersoll-Sergeant Drill | 33,780| | |Company | | |One |High-pressure compressor, Ingersoll-Sergeant Drill | 6,665| | |Company | | |Three |Hydraulic power pumps, George F.

    Blake Manufacturing | 3,075| | |Company | | |Two |General Electric Company's generators coupled to Ball | 7,626| | |and Wood engines | | |------+------------------------------------------------------+--------| | |Total cost of main items of plant | $79,572| |------+------------------------------------------------------+--------| | SUMMARY OF COST OF ONE PLANT. |-------------------------------------------------------------+--------+ |Total cost of main items of plant | $79,572| | | | |Cost of four shields (including installation, demolition, | 103,560| |large additions and renewals, piping, pumps, etc.) | | | | | |Cost of piping, connections, drills, derricks, installation | 101,818| |of offices and all miscellaneous plant | | | | | |Cost of installation, including preparation of site | 39,534| |-------------------------------------------------------------+--------| |Total prime cost of one power-house plant |$324,484| |=============================================================+========|

    The following is a short description of each item of plant in Table 2:

    Boilers.--At each shaft there were three 500-h.p., water-tube boilers, Class F (made by Sterling and Company, Chicago, Ill.). They had independent steel stacks, 54 in. in diameter and 100 ft. above grate level; each had 5,000 sq. ft. of heating surface and 116 sq. ft. of grate area. The firing was by hand, and there were shaking grates and four doors to each furnace. Under normal conditions of work, two boilers at each plant were able to supply all the steam required. The average working pressure of the steam was 135 lb. per sq. in.

    The steam piping system was on the loop or by-pass plan. The diameter of the pipes varied from 14 in. in the main header to 10 in. in the body of the loop. The diameter of the exhaust steam main increased from 8 in. at the remote machines to 20 in., and then to 30 in., at the steam separator, which in turn was connected with the condensers. A pipe with an automatic relief valve from the exhaust to the atmosphere was used when the condensers were shut down. All piping was of the standard, flanged extra-heavy type, with bronze-seated gate-valves on the principal lines, and globe-valves on some of the auxiliary ones.

    There was an 8-in. water leg on the main header fitted with a Mason-Kelly trap, and other smaller water traps were set at suitable intervals.

    Each boiler was fitted with safety valves, and there were automatic release valves on the high-and low-pressure cylinders of each compressor, as well as on each air receiver.

    Buckwheat coal was used, and was delivered to the bins on the Manhattan side by teams and on the Weehawken side by railroad cars or in barges, whence it was taken to the power-house by 2-ft. gauge cars. An average of 20 tons of coal in each 24 hours was used by each plant.

    The water was taken directly from the public service supply main. The daily quantity used was approximately 4,000 gal. for boiler purposes and 4,400 gal. for general plant use. Wooden overhead tanks having a capacity of 14,000 gal. at each plant served as a 12-hour emergency supply.

    Feed Pumps.--There were two feed pumps at each plant. They had a capacity of 700 cu. ft. per min., free discharge. The plungers were double, of 6-in. diameter, and 10-in. stroke, the steam cylinders were of 10-in. diameter and 10-in. stroke. An injector of the "Metropolitan Double-Tube" type, with a capacity of 700 cu. ft. per min., was fitted to each boiler for use in emergencies.

    The feed-water heater was a "No. 9 Cochrane," guaranteed to heat 45,000 lb. of water per hour, and had a total capacity of 85.7 cu. ft. It was heated by the exhaust steam from the non-condensing auxiliary plant.

    Condenser Plant.--There were two surface condensers at each plant.

    Each had a cooling surface sufficient to condense 22,500 lb. of steam per hour, with water at a temperature of 70° Fahr. and barometer at 30 in., maintaining a vacuum of 26 in. in the condenser. Each was fitted with a Blake, horizontal, direct-acting, vacuum pump.

    Circulating-Water Pumps.--Two circulating-water pumps, supplying salt water directly from the Hudson River, were placed on the wharf. They were 8-in. centrifugal pumps, each driven by a 36-h.p., General Electric Company's direct-current motor (220 volts and 610 rev. per min.), the current being supplied from the contractor's power-house generators. The pumps were run alternately 24 hours each at a time. Those on the Manhattan side were 1,300 ft. from the power-house, and delivered their water through a 16-in. pipe; those on the Weehawken side were 450 ft. away, and delivered through a 14-in. pipe.

    There was also a direct connection with the city mains, in case of an accident to the salt-water pumps.

    Low-Pressure Compressors.--At each plant there were three low-pressure compressors. These were for the supply of compressed air to the working chambers of the subaqueous shield-driven tunnels. They were also used on occasions to supply compressed air to the cylinders of the high-pressure compressors, thus largely increasing the capacity of the latter when hard pressed by an unusual call on account of heavy drilling work in the rock tunnels. They were of a new design, of duplex Corliss type, having cross-compound steam cylinders, designed to operate condensing, but capable of working non-condensing; the air cylinders were simple duplex.

    The steam cylinder valves were of the Corliss release type, with vacuum dash-pots. The valves in the air cylinders were mechanically-operated piston valves, with end inlet and discharge. The engines used steam at 135 lb. pressure. The high-and low-pressure steam cylinders were 14 in. and 30 in. in diameter, respectively, with a stroke of 36 in. and a maximum speed of 135 rev. per min. The two air cylinders were 23½ in. in diameter, and had a combined capacity of 35.1 cu. ft. of free air per revolution, and, when running at 125 rev. per min., each machine had an actual capacity of 4,389 cu. ft. of free air per min., or 263,340 cu. ft. per hour.

    The air cylinders were covered by water-jackets through which salt water from the circulating pumps flowed. A gauge pressure of 50 lb. of air could be obtained.

    Each compressor was fitted with an automatic speed and air-pressure regulator, designed to vary the cut-off according to the volume of air required, and was provided with an after-cooler fitted with tinned-brass tube and eight Tobin-bronze tube-plates having 809 sq. ft. of cooling surface; each one was capable of reducing the temperature of the air delivered by it to within 10° Fahr. of the temperature of the cooling water when its compressor was operated at its fullest capacity. From the after-cooler the air passed into a vertical receiver, 4 ft.

    6 in. in diameter and 12 ft. high, there being one such receiver for each compressor. The receivers were tested to a pressure of 100 lb. per sq. in. The after-coolers were provided with traps to collect precipitated moisture and oil. The coolers and receivers were fitted with safety valves set to blow off at 1 lb. above the working pressure. The air supply was taken from without, and above the power-house roof, but in very cold weather it could be taken from within doors.

    High-Pressure Compressors.--There was one high-pressure compressor at each plant. Each consisted of two duplex air cylinders fitted to a cross-compound, Corliss-Bass, steam engine. The two steam cylinders were 14 and 26 in. in diameter, respectively, and the air cylinders were 14¼ in. in diameter and had a 36-in. stroke. The air cylinder was water-jacketed with salt water supplied from the circulating water pumps.

    The capacity was about 1,100 cu. ft. of free air per min. when running at 85 rev. per min. and using intake air at normal pressure, but, when receiving air from the low-pressure compressors at a pressure of 30 lb. per sq. in., the capacity was 3,305 cu. ft. of free air per min.; receiving air at 50 lb. per sq. in., the capacity would have been 4,847 cu. ft. of free air per min. This latter arrangement, however, called for more air than the low-pressure compressors could deliver.

    With the low-pressure compressor running at 125 rev. per min. (its maximum speed), it could furnish enough air at 43.8 lb. per sq. in. to supply the high-pressure compressor running at 85 rev. per min. (its maximum speed); and, with the high-pressure compressor delivering compressed air at 150 lb., the combined capacity of the arrangement would have been 4,389 cu. ft. of free air per min.

    The air passed through a receiver, 4 ft. 6 in. in diameter and 12 ft. high, tested under a water pressure of 225 lb. per sq. in., before being sent through the distributing pipes.

    Hydraulic Power Pumps.--At each power-house there were three hydraulic power pumps to operate the tunneling shields. One pump was used for each tunnel, leaving the third as a stand-by. The duplex steam cylinders were 15 in. in diameter, with a 10-in. stroke; the duplex water rams were 2-1/8 in. in diameter with a 10-in. stroke. The pumps were designed to work up to 6,000 lb. per sq. in., but the usual working pressure was about 4,500 lb. The piping, which was extra heavy hydraulic, was connected by heavy cast-steel screw couplings having a hexagonal cross-section in the middle to enable tightening to be done with a bolt wrench.

    The piping was designed to withstand a pressure of 5,500 lb. per sq. in.

    Electric Generators.--At each plant there were two electric generators supplying direct current for both lighting and power, at 240 volts, through a two-wire system of mains. They were of Type M-P, Class 6, 100 kw., 400 amperes, 250 rev. per min., 240 volts no load and 250 volts full load. They were connected direct to 10 by 20 by 14-in., center-crank, tandem-compound, engines of 150 h.p. at 250 rev. per min.

    A switch-board, with all the necessary fuses, switches, and meters, was provided at each plant.

    Lubrication.--In the lubricating system three distinct systems were used, each requiring its own special grade of oil.

    The journals and bearings were lubricated with ordinary engine oil by a gravity system; the oil after use passed through a "White Star" filter, and was pumped into a tank about 15 ft. above the engine-room floor.

    The low-pressure air cylinders were lubricated with "High Test" oil, having a flash point of 600° Fahr. The oil was forced from a receiving tank into an elevated tank by high-pressure air. When the tank was full the high-pressure air was turned off and the low-pressure air was turned on, in this way the air pressure in the oil tank equalled that in the air cylinder being lubricated, thus allowing a perfect gravity system to exist.

    The steam cylinders and the high-pressure air cylinders were fed with oil from hand-fed automatic lubricators made by the Detroit Lubrication Company, Detroit, Mich.

    "Steam Cylinder" oil was used for the steam cylinders and "High Test" oil (the same as used for the low-pressure air cylinders) for the high-pressure air cylinders. The air cylinder and steam cylinder lubricators were of the same kind, except that no condensers were necessary. The steam cylinder and engine oil was caught on drip pans, and, after being filtered, was used again as engine oil in the bearings.

    The oil from the air cylinders was not saved, nor was that from the steam cylinders caught at the separator.

    Cost of Operating the Power-House Plants.--In order to give an idea of the general cost of running these plants, Tables 3 and 4 are given as typical of the force employed and the general supplies needed for a 24-hour run of one plant. Table 3 gives a typical run during the period of driving the shields, and Table 4 is typical of the period of concrete construction. In the latter case the tunnels were under normal air pressure. Before the junction of the shields, both plants were running continuously; after the junction, but while the tunnels were still under compressed air, only one power-house plant was operated.

    TABLE 3.--COST OF OPERATING ONE POWER-HOUSE FOR 24 HOURS DURING

    EXCAVATION AND METAL LINING.

    +===================+====================+

    No.| Labor. | Rate per day. | Amount. ---+-------------------+--------------------+------------- 6 |Engineers | $3.00 | $18.00 6 |Firemen | 2.50 | 15.00 2 |Oilers | 2.00 | 4.00 2 |Laborers | 2.00 | 4.00 4 |Pumpmen | 2.75 | 11.00 2 |Electricians | 3.50 | 7.00 1 |Helper | 3.00 | 3.00 ---+-------------------+--------------------+------------- Total per day | $62.00 --------------------------------------------+------------- Total for 30 days | $1,860.00 --------------------------------------------+------------- Supplies. -----------------------+--------------------+------------- Coal (14 tons per day) | $3.25 | $45.50 Water | 7.00 | 7.00 Oil (4 gal. per day) | 0.50 | 2.00 Waste (4 lb. per day) | 0.07 | 0.28 Other supplies | 1.00 | 1.00 -----------------------+--------------------+------------- Total per day | $55.78 --------------------------------------------+------------- Total for 30 days | $1,673.00 --------------------------------------------+------------- Total cost of labor and supplies for 30 days| $3,533.00

    +

    Stone-Crusher Plant.--A short description of the stone-crusher plant will be given, as it played an important part in the economy of the concrete work. In order to provide crushed stone for the concrete, the contractor bought (from the contractor who built the Bergen Hill Tunnels) the pile of trap rock excavated from these tunnels, which had been dumped on the piece of waste ground to the north of Baldwin Avenue, Weehawken, N. J.

    The general layout of the plant is shown on Plate XXX. It consisted of a No. 6 and a No. 8 Austin crusher, driven by an Amex, single-cylinder, horizontal, steam engine of 120 h.p., and was capable of crushing about 225 cu. yd. of stone per 10-hour day. The crushers and conveyors were driven from a countershaft, in turn driven from the engine by an 18-in. belt.

    TABLE 4.--COST OF OPERATING THE ONE PLANT FOR 24 HOURS DURING CONCRETE

    LINING.

    +===================+====================+

    No.| Labor. | Rate per day. | Amount. ---+-------------------+--------------------+------------- 2 |Engineers | $3.00 | $6.00 2 |Firemen | 2.50 | 5.00 2 |Pumpmen | 3.00 | 6.00 1 |Foreman Electrician| 6.00 | 6.00 1 |Electrician | 3.00 | 3.00 1 |Laborer | 2.00 | 2.00 ---+-------------------+--------------------+------------- Total per day | $28.00 --------------------------------------------+------------- Total for 30 days | $840.00 --------------------------------------------+------------- Supplies. -----------------------+--------------------+------------- Coal (14 tons per day) | $3.15 | $44.10 Oil (4 gal. per day) | 0.50 | 2.00 Water | 13.00 | 13.00 Other supplies | 2.00 | 2.00 -----------------------+--------------------+------------- Total per day | $61.10 --------------------------------------------+------------- Total for 30 days | $1,833.00 --------------------------------------------+------------- Total cost of labor and supplies for 30 days| $2,673.00

    +

    The process of crushing was as follows: The stone from the pile was loaded by hand into scale-boxes which were lifted by two derricks into the chute above the No. 6 crusher. One derrick had a 34-ft. mast and a 56-ft. boom, and was worked by a Lidgerwood steam hoister; the other had a 23-ft. mast and a 45-ft. boom, and was worked by a "General Electric" hoist. All the stone passed first through the No. 6 crusher, after which it was lifted by a bucket conveyor to a screen, placed about 60 ft. higher than and above the stone bin.

    The screen was a steel chute pierced by 2½-in. circular holes, and was on a slope of about 45°; in order to prevent the screen from choking, it was necessary to have two men continually scraping the stone over it with hoes. All the stone passing the screen was discharged into a bin below with a capacity of about 220 cu. yd. The stone not passing the screen passed down a diagonal chute to a No. 8 crusher, from which, after crushing, it was carried back by a second bucket conveyor to the bin, into which it was dumped without passing a screen. The No.

    8 crusher was arranged so that it could, when necessary, receive stone direct from the stone pile. The cars in which the stone was removed could be run under the bin and filled by opening a sliding door in the bottom of the bin. A track was laid from the bin to connect with the contractor's surface railway in the Weehawken Shaft yard, and on this track the stone could be transported either to the Weehawken Shaft direct, for use on that side of the river, or to the wharf, where it could be dumped into scows for transportation to New York.

    The cars used were 3-cu. yd. side-dump, with flap-doors, and were hauled by two steam Dinky locomotives.

    The average force employed was:

    1 foreman @ $3.00 per day. Supervising.
    24 laborers " 1.75 " " Loading scale-boxes for derricks.
    4 laborers " 1.75 " " Feeding crushers.
    2 laborers " 1.75 " " Watching screens to prevent clogging.
    1 engineer " 4.00 " " Driving steam engine.
    2 engineers " 3.50 " " On the derricks.
    1 night watchman. Watching the plant at night.

    Owing to the constant break-down of machinery, chutes, etc., inseparable from stone-crushing work, there was always at work a repair gang consisting of either three carpenters or three machinists, according to the nature of the break-down.

    The approximate cost of the plant was:

    Machinery $5,850
    Lumber 3,305
    Erection labor 3,999
    ------
    Total $13,154

    The cost of the crushed stone at Weehawken amounted to about $0.91 per cu. yd., and was made up as follows:

    Cost of stone $0.22
    Labor in operation of plant 0.31
    Plant supplies 0.11
    [B]Plant depreciation 0.27
    -----
    Total $0.91

    [B] Assuming that the scrap value of derricks and engines is one-half the cost, crushers one-third the cost, and other items nothing.

    The crushed stone at the Manhattan Shaft cost about $1.04 per cu. yd., the difference of $0.13 from the Weehawken cost being made up of the cost of transfer across the river, $0.08, and transport from the dock to the shaft, $0.05.

    Miscellaneous Plant.--The various pieces of plant used directly in the construction work, such as derricks, hauling engines, pumps, concrete mixers, and forms, will be found described or at least mentioned in connection with the methods used in construction.

    The tunneling shields, however, will be described now, as much of the explanation of the shield-driven work will not be clear unless preceded by a good idea of their design.

    Tunneling Shields.

    During the period in which the original contract drawings were being made, namely, in the latter part of 1903 and the early part of 1904, considerable attention was given to working out detailed studies for a type of shield which would be suitable for dealing with the various kinds of ground through which the shield-driven tunnels had to pass.

    This was done in order that, when the contract was let, the engineer's ideas of the requirements of the shields should be thoroughly crystallized, and so that the contractor might take advantage of this long-thought-out design, instead of being under the necessity of placing a hurried order for a piece of plant on which so much of the safety as well as of the speed of his work depended. Eventually, the contractor took over these designs as they stood, with certain minor modifications, and the shields as built and worked gave entire satisfaction.

    The chief points held in view were ample strength, easy access to the working face combined with ease and quickness of closing the diaphragm, and general simplicity. A clear idea of the main features of the design can be gathered from Fig. 3 and Plate XXXI.

    [A]The interior diameter of the skin was 2 in. greater than the external diameter of the metal lining of the tunnel, which was 23 ft.

    The skin was made up of three thicknesses of steel plate, a ¾-in. plate outside and inside, with a 5/8-in. plate between; thus the external diameter of the skin was 23 ft. 6¼ in. The length over all (exclusive of the hood, to be described later) was 15 ft. 11-7/16 in.

    The maximum overlap of the skin over the erected metal lining was 6 ft. 4½ in., and the minimum overlap, 2 ft.

    There were no inside or outside cover-plates, the joints of the various pieces of skin plates being butt-joints covered by the overlap of adjoining plates. All riveting was flush, both inside and outside. The whole circumference of each skin plate was made up of eight pieces, each of which extended the entire length of the shield, the only circumferential joint on the outside being at the junction of the removable cutting edge (or of the hood when the latter was in position) with the shield proper.

    Forward of the back ends of the jacks, the shield was stiffened by an annular girder supporting the skin, and in the space between the stiffeners of which were set the 24 propelling rams used to shove the shield ahead by pressure exerted on the last erected ring of metal lining, as shown on Plate XXXI.

    To assist in taking the thrust of these rams, gusset-plates were placed against the end of each ram cylinder, and were carried forward to form level brackets supporting the cast-steel cutting-edge segments. The stiffening gussets, between which were placed the rams, were also carried forward as level brackets, for the same purpose. The cast-steel segmental cutting edge was attached to the front of the last mentioned plates.

    The interior structural framing consisted of two floors and three vertical partitions, giving nine openings or pockets for access to the face; these pockets were 2 ft. 7 in. wide, the height varying from 2 ft. 2 in. to 3 ft. 4 in., according to their location. The openings were provided with pivoted segmental doors, which were adopted because they could be shut without having to displace any ground which might be flowing into the tunnel, and while open their own weight tended to close them, being held from doing so by a simple catch.

    [Illustration: PROPOSED SHIELD FOR SUBAQUEOUS TUNNELING GENERAL ELEVATION FIG. 3.]

    For passing through the varied assortment of ground before entering on the true sub-river silt, it was decided to adopt the forward detachable extension, or hood, which has so often proved its worth in ground needing timber for its support, as shown in Fig. 2, Plate XXIX. This hood extended 2 ft. 1 in. beyond the cutting edge, and from the top down to the level of the upper platform. Additional pieces were provided by which the hood might have been brought down as far as the lower platform, but they were not used.

    Special trapezoidal steel castings formed the junction between the hood and the cutting edge. The hood was in nine sections, built up of two ¾-in. and one 5/8-in. skin plates, as in the main body of the skin, and was supported by bracket plates attached to the forward ends of the ram chambers. The hoods were bolted in place, and were removed and replaced by regular cutting-edge steel castings after the shields had passed the river lines.

    The floors of the two platforms, of which there were eight, formed by the division of the platforms by the upright framing, could be extended forward 2 ft. 9 in. in front of the cutting edge, or 8 in. in front of the hood. This motion was given by hydraulic jacks. The sliding platform could hold a load of 7,900 lb. per sq. ft., which was equal to the maximum head of ground and water combined. The uses of these platforms will be described under the heading "Construction." The weight of the structural portion of each shield was about 135 tons.

    The remainder of the shield was the hydraulic part, which provided its motive force and gave the power to the segment erector. The hydraulic fittings weighed about 58 tons per shield, so that the total weight of each shield was about 193 tons. The hydraulic apparatus was designed for a maximum pressure of 5,000 lb. per sq. in., a minimum pressure of 2,000 lb., and a test pressure of 6,000 lb. The actual average pressure used was about 3,500 lb. per sq. in.

    There were 24 shoving rams, with a diameter of 8½ in. and stroke of 38 in. The main ram was single-acting. The packings could be tightened up from the outside without removing the ram, a thing which is of the greatest convenience, and cannot be done with the differential plunger type. Some of the chief figures relating to the shield rams, with a water pressure of 5,000 lb. per sq. in., are:

    Forward force of one ram 275,000 lb.
    Forward force of 24 rams (all) 6,600,000 "
    Forward force of 24 rams 3,300 tons of 2,000 lb.
    Equivalent pressure per square inch of face 105 lb.
    Equivalent pressure per square foot of face 15,200 "
    Pull-back force of one ram 26,400 "
    Pull-back pressure on full area of ram 480 " per sq. in.

    The rams developed a tendency to bend, under the severe test of shoving the shield all closed, or nearly so, through the river silt, and it is probable that it would have been better to make the pistons 10 in. in diameter instead of 8½ in.

    Each sliding platform was actuated by two single-acting rams, 3½ in. in diameter and having a stroke of 2 ft. 9 in. The rams were attached to the rear face of the shield diaphragm inside the box floors, and the cylinders were movable, sliding freely on bearings in the floor. The front ends of the cylinders were fixed to the front ends of the sliding platforms. The cylinder thus supported the front end of the sliding platform, and was designed to carry its half of the load on the platform. Some of the leading figures in connection with the platform rams, at a working pressure of 5,000 lb. per sq. in., are:

    Forward force of each pair of rams (in each platform) 96,000 lb.
    Total area of nose of sliding platform 1,060 sq. in.
    Maximum reaction per square inch on nose 90 lb.
    Maximum reaction per square foot on nose 13,040 "

    Each shield was fitted with a single erector mounted on the rear of the diaphragm. The erector consisted of a box-shaped frame mounted on a central shaft revolving on bearings attached to the shield. Inside of this frame there was a differential hydraulic plunger, 4 in. and 3 in. in diameter and of 48-in. stroke. To the plunger head were attached two channels sliding inside the box frame, and to the projecting ends of these the grip was attached. At the opposite end of the box frame a counterweight was attached which balanced about 700 lb. of the tunnel segment at 11 ft. radius.

    The erector was revolved by two single-acting rams fixed horizontally to the back of the shield above the erector pivot through double chains and chain wheels keyed to the erector shaft.

    The principal figures connected with the erector, assuming a water pressure of 5,000 lb. per sq. in., are:

    Weight of heaviest tunnel segment 2,584 lb.
    Weight of erector plunger and grip 616 "
    Total weight to be handled by the erector ram 3,200 "
    Total force in erector ram moving from center of shield 35,000 "
    Total force in erector ram moving toward center of shield 27,500 "
    Weight at 11-ft. radius which is balanced by counterweight 700 "
    Maximum net weight at 11-ft. radius to be handled by
    turning rams 1,884 "
    Total force of each rotating ram, at 5,000 lb. per sq. in.

    80,000 "
    Load at 11-ft. radius, equivalent to above 3,780 "

    When the shield was designed, a grip was also designed by which the erector could handle segments without any special lugs being cast on them. A bolt was passed through two opposite bolt holes in the circumferential flanges of a plate. The grip jaws closed over this bolt and locked themselves. The projecting fixed ends of the grip were for taking the direct thrust on the grip caused by the erector ram when placing a segment.

    It happened, however, that there was delay in delivering these grips, and, when the shield was ready to start, and the grip was not forthcoming, Mr. Patrick Fitzgerald, the Contractor's Superintendent, overcame this trouble by having another grip made.

    In this design, also, a self-catching bolt is placed through the segment and the grip catches the bolt. In simplicity and effectiveness in working, this new design eventually proved a decided advance on the original one, and, as a result, all the shields were fitted with the new grip, and the original design was discarded.

    The great drawback to the original grip was that the plate swung on the lifting bolt, and thus brought a great strain on the bolt when held rigidly at right angles to the erector arm. The original design was able to handle both A and B segments, and key segments, without alteration; in the new design, an auxiliary head had to be swung into position to handle the key, but this objection did not amount to a practical drawback.

    The operating floor from which the shield was controlled, and at which the valves were situated, was placed above the rams which rotate the erector, and formed a protection for them. The control of the shield rams was divided into four groups: the seven lower rams constituted one group, the upper five, another, and the six remaining on each side, the other two. Each group was controlled by its own stop and release valve.

    Individual rams were controlled by stop-cocks.

    The control of the sliding platform rams was divided into two groups, of which all the rams on the upper floor made one, and all those in the lower floor, the other; here, again, each group had its own stop and release valve, and individual platforms were controlled by stop-cocks arranged in blocks from which the pipes were carried to the rams.

    The in-and-out movements of the erector ram were controlled by a two-spindle, balanced, stop and release valve, controlled by a hand-wheel. The erector rotating rams were controlled by a similar valve, with four spindles, also operated by a single hand-wheel. Both wheels were placed inside the top shield pockets, and within easy reach of the operating platform.

    The hydraulic pressure was brought through the tunnel by a 2-in. hydraulic pipe. Connection with the shield was made by a flexible copper pipe, the 2-in. line being extended as the shield advanced.

    LAND TUNNELS.

    General.

    The following is a brief account of the main features of the "Land Tunnel" work, by which is meant all the part of the structure built without using tunneling shields.

    The Land Tunnels consist of about 977 ft. of double tunnel on the New York side and 230 ft. on the New Jersey side, or a total of 1,207 lin. ft. of double tunnel.

    The general design of the cross-section consists of a semi-circular arch, vertical side-walls and a flat invert. The tunnel is adapted for two lines of track, each being contained in its compartment or tunnel.

    The span of the arch is wider than is absolutely necessary to take the rolling stock, and the extra space is utilized by the provision of a sidewalk or "bench" forming by its upper surface a gangway, out of the way of traffic, for persons walking in the tunnels, and embedded in its mass are a number of vitrified earthenware ducts, for high-and low-tension electric cables.

    The provision of this bench enables its vertical wall to be brought much nearer to the side of the rolling stock than is usually possible, thus minimizing the effects of a derailment or other accident. Refuge niches for trackmen, and ladders to the top of the bench are provided at frequent intervals.

    In cases where a narrow street limits the width of the structure, as on the New York side, the two tunnels are separated by a medial wall of masonry, thus involving excavation over the entire width of both tunnels, and in such case the tunnels are spoken of as "Twin Tunnels"; where the exigencies of width are not so severe, the two tunnels are entirely distinct, and are separated by a wall of rock. This type is found on the Weehawken side.

    The arches are of brick, the remainder of the tunnel lining being of concrete.

    New York Land Tunnels.

    The work on the Land Tunnels on the Manhattan side was carried on from the shaft at 11th Avenue and 32d Street.

    The plans and designs for these tunnels are shown on Plate XXXII. In this short length of about 977 ft. there are no less than nine different kinds of cross-section. The reason for these changes is the fact that the two lines of track are here not straight and parallel to the center line between the tunnels, but are curved, although symmetrical about this center line.

    The various changes of section are to enable the tunnels to be built in straight lengths, thus avoiding the disadvantages attending the use of curved forms, and at the same time minimizing the quantity of excavation, an item which accounts for from 60 to 70% of the total cost of tunnels of this type.

    Of course, there are corresponding and obvious disadvantages in the adoption of many short lengths of different cross-sections, and these disadvantages were well brought out in the course of the work; on the whole, however, they may be said to have justified their adoption.

    These New York Land Tunnels were divided into three contracts, viz.: From Station 190 + 15 (the Portal to the open work of the Terminal Station at the east side of Tenth Avenue, New York City) to Station 197 + 60, called "Section Gy-East." The next contract, called "Section Gy-West Supplementary," extended from Station 197 + 60 to Station 199 + 20, which is the east side of Eleventh Avenue.

    The third contract was called "Section Gy-West," and extended from Station 199 + 20 to Station 231 + 78 (the dividing line between the States of New York and New Jersey). Thus, for nearly all its length, this contract consists of shield-driven tunnel. The portion between Stations 199 + 20 and 199 + 91.5, however, was of the Land Tunnel type, and therefore will be included here. A fourth contract extended from Station 231 + 78 to the Weehawken Shaft at Station 263 + 50, and of this all but 230 ft. was of the shield-driven type, only the portion next to the Weehawken Shaft being of the Land Tunnel type.

    The four contracts were let to one contractor (The O'Rourke Engineering Construction Company), and the work was carried on simultaneously in all four, so that the division into contracts had no bearing on the methods of work adopted, and these will now be described as a whole and with no further reference to the different sections.

    Excavation.

    Work was started on the New York side on April 18th, 1904, the Weehawken shaft being at that date still under construction. As will have been noted in the description of the shafts, the contractor found a shaft already prepared for his use, and cross-drifts at grade and at right angles to the future tunnels, and extending across their entire width.

    The first essential was to get access to the shield chambers, which were to lie about 330 ft. to the west of the shaft, so that the construction of these enlargements in which the shields for the subaqueous tunnels were to be built might be finished as soon as possible and thus allow the earliest possible start to be made with the shield-driven tunnels.

    With this in view, two bottom headings, on the center line of each of the two tracks, were driven westward from the western cross-heading at the foot of the shaft. When about 138 ft. had been made in this way, the two headings were brought together and a break-up was made to the crown level of the tunnel, as the depth of rock cover was doubtful. From this break-up a top heading was driven westward to Station 200 + 30.

    While widening the heading out at Station 200 + 20 the rock was penetrated on the south side. The exposed wet sand and gravel started to run, and, as a consequence, a change in design was made, the shield chambers (and consequently the start of the shield-driven tunnels) being moved eastward from their original location 133 ft. to their present location. A certain amount of time was necessarily spent in making these changes of design, which involved a rearrangement of the whole layout from the Terminal Station to the start of the River Tunnels.

    On July 5th, 1904, however, the new design was formally approved. No sooner had this been decided than a strike arose on the work, and this was not settled until August 1st, 1904, but from that time the work progressed without delay. No further reference will be made to the work in the shield chambers, as that will come under the heading of "River Tunnels," being of the segmental, cast-iron lined type.

    A top heading was now driven over the original bottom heading west of the shaft, and at the same time the original cross-drifts from the shaft were amalgamated with and broken down by a heading driven at the crown level of the "Intercepting Arch" which here cuts across the ordinary run of tunnel at right angles and affords access to the tunnels from the shafts.

    The excavation of the upper portion of the intercepting arch at its southern end gave some trouble, and caused some anxiety, as the rock cover was penetrated and the wet sand and gravel were exposed. This made it necessary to timber all this section heavily, and the tracks of the New York Central Railroad directly above were successfully supported.

    The general way in which this timbering was carried out will be described under the head of "Timbering."

    Meanwhile, the excavation of the tunnels west of the intercepting arch was continued until the North and South Tunnels were taken out to their full outlines, leaving a core of rock between them. This core was gradually removed, and timbering supporting the rock above the middle wall was put in as excavation went on.

    The ground, which was entirely of micaceous schist, typical of this part of Manhattan, seamed with veins of granite, was rather heavy at the west end, or adjacent to the shield chambers, and required complete segmental timbering across the whole span. One heavy fall of rock in the corewall between the North and South Tunnels took place on November 2d, but fortunately did not extend beyond the limits of the permanent work. On November 7th, 1904, the excavation east of the intercepting arch was begun by driving a bottom heading in the South Tunnel.

    This was continued to Station 197 + 14 and then was taken up to the crown level and worked as a top heading with the view of keeping track, by making exploratory borings upward from the roof at frequent intervals, of the rock surface, which was here irregular and not known with any degree of certainty. The work was not pressed with any vigor, because all efforts were then being bent toward excavating from the River Tunnels as much rock as possible.

    In Section Gy-East the conditions were exceptionally variable, as the rock was subject to sudden changes from a soft crumbling mica schist to broad bands of hard granite, and, in addition, the rock surface was very irregular, and, for a good length of this section, was below the crown of the tunnel, a condition which led to the adoption of the cut-and-cover method for part of the work.

    The irregularity in conditions called for varying methods of procedure, but in general the methods were as shown on Plate XXXIII, and described as follows:

    In Solid Rock.--Where there was plenty of good rock cover, a top middle heading was driven, which was afterward widened out to the full cross-section of the twin tunnel arches. If necessary, a few lengths of segmental timbering were put in before taking down the bench, which was generally kept some 40 or 50 ft. behind the breast of the heading. After the bench was down, the middle conduit trench was excavated and the trimming done.

    In Soft Rock.--Where there was not enough rock cover, or where there was actual soft ground in the roof, wall-plate headings at the springing line level were driven ahead of the remainder of the work. The wall-plates were laid in these, the roof was taken out in short lengths, and segmental timbering spanning from wall-plate to wall-plate was put in. The roof being thus held, the bench excavation proceeded without trouble. Where the rock was penetrated and soft ground showed in the roof, poling boards were driven ahead over the crown-bars, as shown in Fig. 4.

    Cut-and-Cover Work.--After some 225 ft. had been driven from the intercepting arch, it was found that the crown of the tunnel was continually in soft ground. To ascertain the extent of this condition the contractor decided to make soundings as far as Tenth Avenue, which was done by sinking trial pits and making wash-borings in the street.

    These soundings showed that there would be soft ground in the crown from Station 194 + 75 to Station 194 + 25 (at one point to a depth of 12 ft. below the crown), and on each side of this section the cover was insufficient from Station 193 + 58 to Station 195 + 30.

    This condition being known, it was decided to adopt cut-and-cover work for this length, the principal reasons being that repairs to sewers, streets, and drains would be no more, and probably less, expensive than with the tunnel method; the underpinning of a heavy brick brewery building adjoining the works on the north side would be facilitated, and the opening in the street, through which muck and materials could be handled, would relieve the congested shaft, through which the large volume of muck from the River Tunnels was then being conveyed.

    On the other hand, the cut-and-cover method was adversely affected by the presence of a heavy timber trestle built down the south side of the street and over which passed all the excavation from the Terminal Station, amounting to a very heavy traffic. As this trestle had to be supported, it complicated the situation considerably. Very little active progress was made between June, 1905, and April, 1906, as the contractor's energies during that time were much taken up with the progress of the shield-driven tunnels.

    In April, 1906, preparations were made to start a 50-ft. length of open cut, rangers being fixed and sheathing driven; and the sewer which ran down the middle of this street was diverted to the outside of the open-cut length.

    April and May were occupied in driving the sheathing down to rock, supporting the trestle, underpinning the adjoining brewery, and excavating the soft material above the rock. On June 2d, 1906, rock was reached, and, by July 31st, the excavation was down to subgrade over nearly the whole 50 ft. in the first length. In the meantime another length was opened up, and eventually a third.

    The surface of the rock now seemed to be rising, and the heavy buildings had been passed, so that tunneling was reverted to for the rest of the work, though many difficulties were caused by soft rock in the roof from time to time.

    [Illustration: METHOD OF DRIVING ROOF LAGGING IN SOFT GROUND. FIG. 4.]

    When the excavation for the open-cut work of the Terminal Station had advanced to the line of Tenth Avenue, the contractor started a heading from this point and drove westward under Tenth Avenue until the headings driven eastward from the cut-and-cover portion, were met.

    This was done to expedite the work under Tenth Avenue, where the ground was not very good, where there were several important gas and water mains in the street, and where, moreover, the tunnels were of exceptionally large span (24 ft. 6 in.), making a total width of some 60 ft. for the excavation. The excavation for the New York Tunnels was practically finished in January, 1908.

    Drilling and Blasting.--The foregoing short description will serve to show in a general way the scheme adopted in making the excavation. A few details on drilling and blasting methods may not be out of place.

    Percussive drills run by air pressure were used. They were Ingersoll-Sergeant, Nos. 3½, A-86, C-24, and F-24. The air came from the high-pressure compressor previously described. This compressor, without assistance, could supply air for nine drills, but, when fed by compressed air from the lower pressure, its capacity was increased three or four times.

    The air was compressed to 100 lb. per sq. in. in the power-house, and was delivered at about 80 lb. per sq. in. at the drills. A 3-in. air line was used. The drill steel was 1-1/8-to 1-3/8-in. octagonal. The holes were about 3¼ in. in diameter at starting and 2-5/8 in. at the full depth of 10 ft. The powder used on the New York side was 40% Forcite, the near presence of heavy buildings and lack of much rock cover necessitating light charges and many holes spaced close together.

    To compensate the contractor for the inevitable excavation done outside the neat lines of the masonry lining, the excavation was paid for to the "Standard Section Line" which was 12 in. outside the neat lines on top and sides and 6 in. outside at the bottom of the cross-section. The actual amount of excavation done was about 11% greater than that paid for. The distance excavated beyond the neat line, because of the very heavy timbering necessary, was about 2.1 ft. instead of the 1 ft. allowed, and at the bottom about 0.85 ft. instead of the 0.50 ft. paid for.

    For a period of 5 months detailed records were kept of the drilling and blasting. About 12,900 cu. yd. of excavation are included. A sketch and table showing the method of driving the heading, the number and location of the holes drilled, and the amount of powder used, is given in Fig. 5.

    From this and similar figures the information in Table 5 is derived.

    TABLE 5.

    +========================+=======+=======+=======+======+=======+======|

    | | FEET OF HOLE | POUNDS OF POWDER |

    | |DRILLED PER CUBIC YARD | USED PER CUBIC YARD |

    | | OF EXCAVATION. | OF EXCAVATION. |

    | +-------+-------+-------+------+-------+------| |Portion of excavation. |15-ft. |19-ft. |24-ft. | | | | | | 4-in. | 6-in. | 6-in. |15-ft.|19-ft. |24-ft.| | |span-- |span-- |span-- |4-in. | 6-in. | 6-in.| | | twin | twin | twin | | | | | |tunnel.|tunnel.|tunnel.| | | | |------------------------+-------+-------+-------+------+-------+------+ |Wall-plate heading[C] | 13.0 | 10.97 | 10.97 |3.77 | 2.85 | 2.85 | | | | | | | | | |Total heading[C] | 7.87 | 8.17 | 7.81 |2.31 | 2.02 | 1.78 | | | | | | | | | |Bench and raker bench[C]| 5.97 | 6.15 | 7.56 |0.94 | 0.93 | 1.13 | | | | | | | | | |Trench[C] | 9.82 | 15.96 | 18.10 |1.84 | 2.49 | 2.73 | |------------------------+-------+-------+-------+------+-------+------+ |Average for section[C] | 6.69 | 7.43 | 8.95 |1.28 | 1.30 | 1.45 | |------------------------+-------+-------+-------+------+-------+------| |Actual amount[D] | 6.82 | 7.27 | 8.95 |1.22 | 1.24 | 1.27 | +========================+=======+=======+=======+======+=======+======+

    [C] Figures taken from typical cross-sections.

    [D] This gives the actual amount of drilling done and powder used per cubic yard for the whole period of 5 months of observation, but as this length included 280 ft. of heading and only 220 ft. of bench, the average figures (for powder especially) are too low.

    Table 6 gives the rate and cost of drilling, and the cost of powder. It will be seen that the average rate of drilling was 2.71 ft. per hour per drill or 27.1 ft. per drill per shift.

    Table 7 shows the result of observation as to the time taken in various subdivisions of the drilling operations. These observations were not carried on for a long enough period to give correct results, but the percentages of time spent on each division of the operation are believed to be about right. The headings of this table are self-explanatory. The necessary delays include all time spent in changing bits, making air-line connections, etc. The unnecessary delays are stoppages caused by lack of supplies or insufficient air pressure.

    By Table 6 it will be noticed that the cost of labor for drilling and sharpening steels was about $0.29 per lin. ft. of hole drilled. The total cost, including repairs, supply of air, etc., came to about $0.38, as will be seen from Table 8.

    Timbering.--On the New York side nearly the whole length of the excavation needed timbering, to a greater or less extent, and for the most part required timbering of quite a heavy type.

    TABLE 6.--ROCK TUNNEL EXCAVATION UNDER 32D STREET, EAST OF CUT-AND-COVER

    SECTION. DRILLING AND BLASTING.--DETAILED COST OF LABOR IN DRILLING,

    ALSO QUANTITY AND COST OF POWDER USED.

    +=====================================================================+

    | DRILLING AND BLASTING. |

    |-----+-----+------+------+------+-----+-----+------+-----+-----+-----| |Type.|Date.|Total feet drilled. | No. drill shifts| Feet drilled | | | | | | | of (10-hour.) |per man per hour.| | +-----+------+------+------+-----+-----+------+-----+-----+-----+ | |1907 |Head- |Bench |Total |Head-|Bench|Total |Head-|Bench|Total| | | | ing | | | ing | | | ing | | | |-----+-----+------+------+------+-----+-----+------+-----+-----+-----+ |Ke.|May | 2,971| 5,578| 8,549| 98 | 204 | 302 |3.031|2.734|2.831| | |June | 2,093| 6,194| 8,287| 85 | 223 | 308 |2.462|2.777|2.691| | |July | | 7,627| 7,627| | 268 | 268 | |2.845|2.845| | |Aug. | | 2,552| 2,552| | 95 | 95 | |2.688|2.688| | |Sept.| | 2,133| 2,133| | 79 | 79 | |2.700|2.700| | +-----+------+------+------+-----+-----+------+-----+-----+-----+ | |Total| 5,064|24,084|29,148| 183 | 869 |1,052 |2.767|2.77 |2.77 | |-----+-----+------+------+------+-----+-----+------+-----+-----+-----+ |Ki.|May | 6,976| | 6,976| 216 | | 216 |3.229| |3.229| | |June | 4,089| | 4,089| 135 | | 135 |3.029| |3.029| | |July | | 3,733| 3,733| | 140 | 140 | |2.666|2.666| | |Aug. | | 6,715| 6,715| | 249 | 249 | |2.769|2.769| | |Estim| |14,742|14,742| | 46 | 546 | |2.700|2.700| | +-----+------+------+------+-----+-----+------+-----+-----+-----+ | |Total|11,065|25,190|36,255| 351 | 935|1,286 |3.152|2.694|2.819| |-----+-----+------+------+------+-----+-----+------+-----+-----+-----+ |Ko.|May | | 1,617| 1,617| | 55| 55 | |2.921|2.921| | |June | | 2,948| 2,948| | 107| 107 | |2.755|2.755| | |July | | 3,734| 3,734| | 131| 131 | |2.850|2.850| | |Aug. | | 8,260| 8,260| | 290| 290 | |2.848|2.848| | |Estim| | 4,787| 4,787| | 285| 285 | |1.180|1.680| | +-----+------+------+------+-----+-----+------+-----+-----+-----+ | |Total| |21,346|21,346| | 868| 868 | |2.460|2.460| |-----+-----+------+------+------+-----+-----+------+-----+-----+-----+ |Grand|Total|16,129|70,620|86,749| 534 |2,672|3,206 |3.020|2.710|2.710| +=====+=====+======+======+======+=====+=====+======+=====+=====+=====+

    +==================================================+=====================+

    | DRILLING AND BLASTING | POWDER USED. |

    |-----+----------+------+--------------------------+--------+-------+----+ | | | | Cost of labor only. | | | | | | | | Drilling and sharpening. | | | | | | | +------+------+-------+----+ | | | | | | | | | Per | | | Cost | | | | | | | | cubic | | | per | | | | | | | | yard. | | | cubic | | | | | | | | | | |yard at| | | | | | | | | | | 11 | | | | | | | | | | | cents | | | | | | | | | | | per | | | | | | | | | | |pound. | | | +----------+------+------+------+-------+----+--------+-------+----+ |Type.| Quantity | |Total.| Per |Actual.|Paid| Total |Actual.|Paid| | | of | | |linear| |for |Quantity| |for.| | |excavation| | |feet. | | | | | | | | in cubic | | | | | | | | | | | yards. | | | | | | | | | | +----------+------+------+------+-------+----+--------+-------+----+ | | Actual. | Paid | $ | $ | $ | |Pounds. | $ | $ | | | [E] | for | | | | | | | |

    | | | [F] | | | | | | | |

    |-----+----------+------+------+------+-------+----+--------+-------+----+ |Ke.| 1,736 | 1,664| 2,331| 0.27 | 1.34 |1.40| 1,595 | 0.10 |0.10| | | 809 | 698| 2,440| 0.29 | 3.01 |3.49| 1,960 | 0.27 |0.31| | | 1,022 | 960| 2,031| 0.26 | 1.98 |2.11| 966 | 0.10 |0.11| | | 743 | 716| 640| 0.25 | 0.86 |0.89| 430 | 0.06 |0.07| | | 238 | 238| 533| 0.25 | 2.24 |2.24| 280 | 0.13 |0.13| | |----------+------+------+------+-------+----+--------+-------+----+ | | 4,548 | 4,276| 7,975| 0.27 | 1.75 |1.87| 5,231 | 0.13 |0.13| |-----+----------+------+------+------+-------+----+--------+-------+----+ |Ki.| 614 | 527| 1,604| 0.23 | 2.61 |3.04| 1,230 | 0.22 |0.26| | | 357 | 259| 1,234| 0.30 | 3.45 |4.76| 1,036 | 0.32 |0.44| | | 530 | 404| 1,084| 0.29 | 2.04 |2.68| 550 | 0.11 |0.15| | | 925 | 890| 1,901| 0.28 | 2.05 |2.13| 905 | 0.10 |0.11| | | 3,254 | 2,908| 4,570| 0.31 | 1.40 |1.57| 2,470 | 0.08 |0.09| | |----------+------+------+------+-------+----+--------+-------+----+ | | 5,680 | 4,988|10,393| 0.29 | 1.83 |2.08| 6,191 | 0.12 |0.14| |-----+----------+------+------+------+-------+----+--------+-------+----+ |Ko.| 250 | 188| 471| 0.29 | 1.88 |2.50| 376 | 0.17 |0.22| | | 496 | 347| 883| 0.29 | 1.78 |2.54| 357 | 0.08 |0.11| | | 626 | 606| 1,003| 0.27 | 1.60 |1.65| 609 | 0.11 |0.11| | | 718 | 709| 2,161| 0.26 | 3.00 |3.04| 918 | 0.14 |0.14| | | 605 | 535| 2,397| 0.50 | 3.96 |4.48| 762 | 0.14 |0.16| | |----------+------+------+------+-------+----+--------+-------+----+ | | 2,695 | 2,385| 6,915| 0.32 | 2.57 |2.90| 3,022 | 0.12 |0.14| | |---------+-------+------+------+-------+----+--------+-------+----+ | |12,923 |11,649|25,283| 0.29 | 1.96 |2.17|14,444 | 0.12 |0.14| +=====+==========+======+======+======+=======+====+========+=======+====+

    The work done during the 5 months when these analyzed cost figures were kept includes 280 ft. of bench and 220 ft. of heading. This excess of bench over heading causes the general average amounts per cubic yard to be too low.

    [E] Actual amount of excavation.

    [F] Amount of excavation paid for.

    [Illustration: 24' 6" SPAN TWIN TUNNELS DETAILS OF METHOD OF DRILLING

    AND BLASTING IN A TYPICAL (NOT EXACT AVERAGE) SECTION]

    +---------+--------+--------+-----+-----+------+------+-------+ | Drilling and Firing Data for | | Each Sub-division of Section | |---------+--------+--------+-----+-----+------+------+-------| | Sub | Volume | No. of | No. | No. |Total |Linear| Total | |divisions|of each |sets of | of | of | lbs. | feet |length | | | sub- | holes |holes|times| of | of |drilled| | |division| | in |fired|powder|tunnel| | | |paid for| | set | | per |broken| | | | | | | | hole | | | | | | | | |fired | | | |---------+--------+--------+-----+-----+------+------+-------| | a | b | c | d | e | f | g | h | |---------+--------+--------+-----+-----+------+------+-------| | A | 17.775 | {[G] 1 | 6 | 3 | 4.50 | | |

    | | | {[H] 1 | 9 | 1 | 1.50 | | |

    | | | {[I] 1 | 6 | 1 | 1.00 | | |

    | | | {[J] 1 | 6 | 1 | 0.75 | 6.0 | 195 | | | | | | | | | | |---------+--------+--------+-----+-----+------+------+-------| | A' | 1.00 | 2 | 3-4 | 1 | 0.25 | 5.0 | 21 | |---------+--------+--------+-----+-----+------+------+-------| | B | 5.925 | {[G] 2 | 3-4 | 1 | 1.00 | 4.0 | 35 | |---------+--------+--------+-----+-----+------+------+-------|

    | C | | {[K] 1 | 3 | 2 | 1.125| | |

    | | 33.33 | 4 | 7 | 1 | 1.125| 5.0 | 186 | |---------+--------+--------+-----+-----+------+------+-------| | D | 6.665 | 2 | 5-6 | 1 | 0.75 | 3.0 | 33 | |---------+--------+--------+-----+-----+------+------+-------| | | | | | | | | |=========+========+========+=====+=====+======+======+=======| | E | 50.00 | | 5 | 1 | 1.50 | 5.0 | 405 | |---------+--------+--------+-----+-----+------+------+-------|

    | F | 88.88 |{ 10.5| 4 | 2 | 1.50 | | |

    | | |{[L] 5.0| 4 | 1 | 1.50 | 4.0 | 682 |

    |---------+--------+--------+-----+-----+------+------+-------| | G | 22.22 | 5.5| 4 | 2 | 1.00 | 5.0 | 132 | |---------+--------+--------+-----+-----+------+------+-------| | | | | | | | | |=========+========+========+=====+=====+======+======+=======| | H | 9.77 |{ 5 | 3 | 1 | 0.50 | | | | | |{ 4 | 6 | 1 | 0.50 | 6.0 | 156 | |---------+--------+--------+-----+-----+------+------+-------| | I | 26.66 | 8 | 5 | 1 | 1.00 | 6.0 | 252 | |---------+--------+--------+-----+-----+------+------+-------| | | | | | | | | | | |========+=====+=====+======+======+=======| | | | | | | | | | | | | | | |========+=====+=====+======+======+=======| | | | | +---------+--------+--------+-----+-----+------+------+-------+

    +---------+------+-------+------+------+---------+-------+------+ | Drilling and Firing Data for | | Total Sections | |---------+------+-------+------+------+---------+-------+------| | Sub |Total |Length | Cu. | Cu. | Total | Total | Total| |divisions|length|drilled| yds. | yds. | lbs. of |lbs. of| lbs. | | | of | per | per | per | powder | powder| of | | |simi- |linear |linear|linear| per | per |powder| | |lar |foot of| foot | foot | linear | foot | per | | |head- |tunnel | of | of | foot of |drilled|cubic | | |ings | |tunnel|tunnel| tunnel | | yard | |---------+------+-------+------+------+---------+-------+------| | a | i | j | k | l | m | n | o | |---------+------+-------+------+------+---------+-------+------| | A | |Sigma | | | | | | | | | c + d |b + i | j |c + d + f| m | m | | | | ----- |------| --- | ----- | --- | --- | | | | g | g | k | g | j | k | | | 2 | 65.00 | 5.925|10.97 | 17.00 | 0.261 |2.848 | |---------+------+-------+------+------+---------+-------+------|

    | A' | 2 | 8.40 | 0.400|21.00 | 0.70 | 0.166 |1.750 |

    |---------+------+-------+------+------+---------+-------+------| | B | 2 | 17.50 | 2.962| 5.90 | 3.50 | 0.200 |1.181 | |---------+------+-------+------+------+---------+-------+------|

    | C | | | | | | | |

    | | 1 | 37.20 | 6.666| 5.58 | 6.975 | 0.187 |1.046 | |---------+------+-------+------+------+---------+-------+------| | D | 2 | 22.00 | 4.444| 4.95 | 5.500 | 0.250 |1.237 | |---------+------+-------+------+------+---------+-------+------| |Total for| |150.10 |20.397| 7.81 | 33.675 | 0.227 |1.778 | | Heading | | | | | | | | |=========+======+=======+======+======+=========+=======+======|

    | E | 1 | 81.00 |10.000| 8.10 | 13.500 | 0.167 |1.350 |

    |---------+------+-------+------+------+---------+-------+------|

    | F | | | | | | | |

    | | 1 |170.50 |22.222| 7.67 | 23.230 | 0.136 |1.046 | |---------+------+-------+------+------+---------+-------+------| | G | 1 | 26.40 | 4.444| 5.94 | 4.400 | 0.166 |0.990 | |---------+------+-------+------+------+---------+-------+------| |Total for| |277.90 |36.666| 7.56 | 41.150 | 0.150 |1.133 | | Bench | | | | | | | | |=========+======+=======+======+======+=========+=======+======|

    | H | | | | | | | |

    | | 1 | 26.00 | 1.628|15.96 | 3.250 | 0.125 |1.995 | |---------+------+-------+------+------+---------+-------+------|

    | I | 2 | 84.00 | 4.444|18.90 | 13.333 | 0.158 |3.000 |

    |---------+------+-------+------+------+---------+-------+------| |Total of | |110.00 | 6.072|18.10 | 16.583 | 0.151 |2.731 | | Trench | | | | | | | | |=========+======+=======+======+======+=========+=======+======| |Total for| |548.00 |63.135| 8.95 | 91.408 | 0.172 |1.446 | | Whole | | | | | | | | |Section | | | | | | | | |=========+======+=======+======+======+=========+=======+======| |Powder taken at 0.5 lb. per stick | +---------+------+-------+------+------+---------+-------+------+

    [G] 6 Cut Holes-8 feet (Black circle)

    [H] 9 First Side Rd. and Bottom-7 feet (Circle with dot in it)

    [I] 6 Back Round-7 feet (Circle with line in it)

    [J] 6 Top Back Round-7 feet (Circle with x in it)

    [K] A' 7 Holes-3 feet (Open circle)

    [L] line holes (Plus sign)

    TABLE 7.--Analysis of Drilling Time on Section Gy-East.

    +========+======+========+=====+=====+=======+========+========+=======+

    | | | | AVERAGE TIME TAKEN: |

    |Position|Nature| No. of |-----+-----+-------+--------+--------+-------| | in | of | Drill | | | | | | | |Section.|Rock. | Shifts |Set- |Dril-|Neces- |Unneces-| Taking |Loading| | | |observed|ting |ling.| sary | sary | down | and | | | | for | up. | |delays.|delays. |machine.|firing.| | | |average.| | | | | | | |--------+------+--------+-----+-----+-------+--------+--------+-------| | | | |h. m.|h. m.| h. m. | h. m. | h. m. | h. m. | | | | |-----+-----+-------+--------+--------+-------| |Heading |Quartz| 8 |0:38 |4:52 | 1:40 | | 0:05 | 0:04 | | | | | | | | | | | |Heading | Hard | 1 |0:15 |8:00 | 1:45 | | | | | | mica | | | | | | | | | |schist| | | | | | | | | | | | | | | | | | | Bench |Quartz| 23 |1:23 |5:57 | 2:23 | 0:05 | 0:05 | 0:07 | | | | | | | | | | | | Bench |Medium| 16 |1:10 |6:08 | 1:50 | 0:12 | 0:07 | 0:07 | | | mica | | | | | | | | | |schist| | | | | | | | | | | | | | | | | | | Center |Medium| 10 |0:58 |5:53 | 1:33 | 0:06 | 0:12 | 0:30 | | trench | mica | | | | | | | | | |schist| | | | | | | | | | | | | | | | | | | Center | Soft | 9 |1:10 |6:40 | 1:17 | 0:10 | 0:20 | 0:23 | | trench | mica | | | | | | | | | |schist| | | | | | | | |--------+------+--------+-----+-----+-------+--------+--------+-------| |General | | 67 |1:08 |5:58 | 1:53 | 0:07 | 0:09 | 0:12 | |average | | | | | | | | | |--------+------+--------+-----+-----+-------+--------+--------+-------| | Per- | | |11.3%|59.7%| 18.9% | 1.1% | 1.5% | 2% | |centage | | | | | | | | | +========+======+========+=====+=====+=======+========+========+=======+

    +========+======+=========+========+======+======+========+

    | | | AVERAGE TIME TAKEN: | FEET DRILLED. |

    |Position|Nature|---------+--------+------+------+--------| | in | of | | | | | | |Section.|Rock. | Total |Mucking.|Total.| Per | Per | | | |drilling.| | |shift.|working | | | | | | | | hour. | | | | | | | | | |--------+------+---------+--------+------+------+--------| | | | h. m. | h. m. |h. m. | | | | | |---------+--------+------+------+--------| |Heading |Quartz| 7:19 | 2:41 |10:00 | 22.0 | 2.86 | | | | | | | | | |Heading | Hard | 10:00 | |10:00 | 42.0 | 4.20 | | | mica | | | | | | | |schist| | | | | | | | | | | | | | | Bench |Quartz| 10:00 | |10:00 | 25.9 | 2.59 | | | | | | | | | | Bench |Medium| 9:34 | 0:26 |10:00 | 22.22| 2.32 | | | mica | | | | | | | |schist| | | | | | | | | | | | | | | Center |Medium| 9:12 | 0:48 |10:00 | 22.0 | 2.39 | | trench | mica | | | | | | | |schist| | | | | | | | | | | | | | | Center | Soft | 10:00 | |10:00 | 26.44| 2.64 | | trench | mica | | | | | | | |schist| | | | | | |--------+------+---------+--------+------+------+--------| |General | | 9:27 | 0:33 |10:00 | 24.1 | 2.54 | |average | | | | | | | |--------+------+---------+--------+------+------+--------| | Per- | | 94.5% | 5.5% | 100% | | | |centage | | | | | | | +========+======+=========+========+======+======+========+

    TABLE 8.--ANALYZED COST OF DRILLING.

    +=============+===========================+===========================+

    | | COST PER FOOT OF HOLE | COST PER DRILL SHIFT |

    |Item of Cost.| DRILLED. | | | +-------+-----+-----+-------+-----+------+------+-------+ | | 15 ft | 9 ft|24 ft|Average|15 ft|19 ft |24 ft |Average| | | 4 in | 6 in| 6 in| | 4 in| 6 in | 6 in | | |-------------+-------+-----+-----+-------+-----+------+------+-------+ |Drilling | $0.25 |$0.28|$0.31| $0.28 |$6.95| $7.75| $7.60| $7.45 | |labor | | | | | | | | | | | | | | | | | | | |Sharpening | 0.02 | 0.02| 0.01| 0.016| 0.58| 0.42| 0.34| 0.43 | | | | | | | | | | | |Drill steel | 0.007|0.007|0.006| 0.007| 0.19| 0.20| 0.15| 0.19 | |(5 in. per | | | | | | | | | |drill shift) | | | | | | | | | | | | | | | | | | | |Drill repairs| 0.02 | 0.02| 0.02| 0.02 | 0.61| 0.59| 0.42| 0.54 | | | | | | | | | | | |High-pressure|[M]0.05| 0.04| 0.07| 0.07 | 1.39| 1.86| 1.67| 1.82 | |air | | | | | | | | | |-------------+-------+-----+-----+-------+-----+------+------+-------+ |Totals | $0.35 |$0.38|$0.41| $0.385|$9.67|$10.82|$10.18|$10.43 | +=============+=======+=====+=====+=======+=====+======+======+=======+

    [M] This is an estimated figure, ascertained by taking a proportion of the whole charge for plant running.

    General Methods.--Whenever any considerable support was needed for the ground, segmental timbering was used. In most cases, this was supported by wall-plates at the springing line, and was set with an allowance for settlement, so that it would be clear of the work when the masonry lining was put in. As the twin-tunnel section involved the excavation of the North and South Tunnels at the same time, the cross-section of the upper part of the excavation consisted of two quadrants rising from the springing line and connected at the top by a horizontal piece from 19 to 28 ft. in length. This made a rather flat arch to support by timbering.

    The timber for the segmental work was 12 by 12-in. yellow pine. In light ground the bents were spaced at 5-ft. centers, in heavy ground 2-ft. 6-in. centers.

    When the soft ground in the roof was struck, posts had to be used in the heading to support the caps. When the bench was removed, the posts were replaced by others down to the bottom of the excavation. These long posts were a great hindrance to all the work, and each replacement of short posts by long ones meant a settlement of the caps; consequently, it was decided to use in the section east of the cut-and-cover, where all the ground was heavy, a temporary inner bent of segmental timber, within and reinforcing the permanent bent, and resting on separate wall-plates. This is shown by Fig. 6. These temporary bents were inside the work, and were removed as the arch was built.

    However, the caps settled considerably in some cases, so that it was not possible to do away with posting entirely.

    In heavy ground the caps were set about 1 ft. above the neat line of the crown of the brick arch, in some cases they were set only 6 in. above, but the settlement was often more than this, causing great trouble in cutting out the encroaching timber when the arch had to be built.

    [Illustration: DETAILS OF LONGITUDINAL SECTIONAL SHOWING METHOD OF

    PLACING LAGGING IN CROWN WITH SOFT ROOF TYPICAL SECTION LOOKING EAST

    FIG. 6.]

    In the tunnels east of the cut-and-cover portion, wall-plate headings were driven (shown by areas marked A on Fig. 5), and, when a length of wall-plate had been set, the full-width heading was advanced a foot or two at a time, the timber segmental bents being set up as soon as possible; lagging was then driven over the cap into the soft ground.

    Fig. 6 shows the double set of segmental bents adopted in the 15-ft. 4-in. twin tunnels east of the cut-and-cover section.

    When the soft ground came down so low as to interfere with the excavation of the wall-plate headings, a small heading was driven into the soft ground on the line of the ends of the caps, and lagging was driven down from this to the wall-plate heading, as illustrated in Fig. 4.

    In the 19-ft. 6-in. tunnels the wall-plate for the inner bent was supported by a side-bench, termed the "Raker" bench. This was left in position until the rest of the bench and the middle subgrade conduit trench had been excavated; it was then possible to support the caps by two rows of posts from subgrade level, take out the inner bents, and excavate the raker bench.

    The 24-ft. 6-in. twin tunnels, which are at the extreme eastern end of this section, adjoining the open-cut work of the Terminal Station, and under Tenth Avenue, were driven from the Terminal Station-West, and the timbering had to be made very secure on account of the pipes and sewers in the street above. Detailed records were kept of the amount of timber used and the cost of labor and material expended in timbering. These records cover the same portion of tunnel as that for which the detailed records of drilling costs, previously referred to, were kept.

    These records are shown in Tables 9 and 10. It will be noted that the timber used in blocking, that is, filling up voids outside the main timbering, amounted to more than two-thirds of the total timber, and that the cost of labor in erecting the timbering exceeds the prime cost of the timber by about one-third.

    The following distinction is made between permanent and temporary timbering: The permanent timbering is that which is concreted in when the masonry is built; the temporary consists of the lower bents and posts, which have to be removed when the masonry is built.

    Force Employed in Excavation.--A typical day's working force for drilling, blasting, mucking, and timbering is shown in Table 11.

    Where there was any large quantity of soft ground in the roof, the timber gang was much larger than shown in Table 11, and was helped by the mucking gang. The drillers did most of the mucking out of the heading before setting up the drills.

    Excavation of Weehawken Rock Tunnels.--This subject may be dismissed in a few words, as very few features of interest were called into play.

    The rock was of good quality, being the sandstone typical of this part of the country. Little or no timbering was needed, there were no buildings above the tunnel to be taken care of, and large charges of powder could be used.

    TABLE 9.--SUPPLEMENTARY ANALYSIS OF TIMBERING, ROCK TUNNEL EXCAVATION

    UNDER 32D STREET, EAST OF CUT-AND-COVER SECTION. ANALYZED COST OF

    TIMBERING, PER FOOT RUN AND PER BENT.

    +=============================+================================ | | Ke | |--------+------------+---------- | |Per foot|Per bent, |Per cubic | |run of |3 ft, 6 in.,|yard | |tunnel |center to |excavation | | |center | |-----------------------------+--------+------------+----------

    |PERMANENT TIMBERING. | | |

    |Lumber in feet, B. M. | | | | Upper Bent. | 274 | 685 | 7.8 | Blocking. | 294 | 735 | 8.3 | Total. | 568 | 1,420 | 16.1 |Cost, in dollars. | | | | Lumber. | 23.75| 59.38 | 0.67 | Labor. | 37.50| 93.75 | 1.06 | Total. | 61.25| 153.13 | 1.73 | | | |

    |TEMPORARY TIMBERING. | | |

    |Lumber in feet, B. M. | | | | Lower Bent. | 479 | 11.97 | 13.6 | Blocking. | 193 | 483 | 5.5 | Total. | 672 | 16.80 | 19.1 |Cost, in dollars. | | | | Lumber. | 29.13| 72.81 | 0.82 | Erection labor. | 28.85| 72.13 | 0.82 | Removal labor. | 8.29| 20.73 | 0.23 | Total labor. | 37.14| 92.86 | 1.05 | Total. | 66.27| 165.67 | 1.87 | | | |

    |GRAND TOTAL. | | |

    |Lumber in feet, B.

    M. |1,240 | 3,100 | 35.2 |Cost, in dollars. | | | | Lumber. | 52.88| 132.19 | 1.49 | Labor. | 74.64| 186.61 | 3.60 | Total. | 127.52| 318.80 | |-----------------------------+--------+------------+---------- | | Ki | |--------+------------+---------- | |Per foot|Per bent, |Per cubic | |run of |3 ft, 6 in.,|yard | |tunnel |center to |excavation | | |center | |-----------------------------+--------+------------+----------

    |PERMANENT TIMBERING. | | |

    |Lumber in feet, B. M. | | | | Upper Bent. | 227 | 830 | 5.3 | Blocking. | 164 | 601 | 3.8 | Total. | 391 | 1,431 | 9.1 |Cost, in dollars. | | | | Lumber. | 16.84| 61.56 | 0.39 | Labor. | 12.82| 46.88 | 0.30 | Total. | 29.66| 108.44 | 0.69 | | | |

    |TEMPORARY TIMBERING. | | |

    |Lumber in feet, B. M. | | | | Lower Bent. | 186.33| 681.25 | 4.33 | Blocking. | 42.80 156.50 | 0.99 | Total. | 229.13| 837.75 | 5.32 |Cost, in dollars. | | | | Lumber. | 9.65| 35.31 | 0.22 | Erection labor. | 10.38| 37.97 | 0.24 | Removal labor. | 9.74| 34.09 | 0.23 | Total labor. | 20.12| 72.06 | 0.47 | Total. | 29.77| 107.37 | 0.69 | | | |

    |GRAND TOTAL. | | |

    |Lumber in feet, B.

    M. | 6.20| 22.69 | 14.4 |Cost, in dollars. | | | | Lumber. | 26.49| 96.87 | 0.61 | Labor. | 32.94| 118.94 | 0.77 | Total. | 59.43| 215.81 | 1.38 |-----------------------------+--------+----------------------- | | Ko | |--------+------------+---------- | |Per foot|Per bent, |Per cubic | |run of |3 ft, 6 in.,|yard | |tunnel |center to |excavation | | |center | |-----------------------------+--------+------------+----------

    |PERMANENT TIMBERING. | | |

    |Lumber in feet, B. M. | | | | Upper Bent. | 261 | 962 | 4.1 | Blocking. | 408 | 1,508 | 6.5 | Total. | 669 | 24.70 | 10.5 |Cost, in dollars. | | | | Lumber. | 28.00| 103.38 | 0.44 | Labor. | 29.79| 110.00 | 0.47 | Total. | 57.79| 213.38 | 0.91 | | | |

    |TEMPORARY TIMBERING. | | |

    |Lumber in feet, B. M. | | | | Lower Bent. | 350 | 1,291 | 5.5 | Blocking. | 61 | 227 | 1.0 | Total. | 411 | 1,518 | 6.5 |Cost, in dollars. | | | | Lumber. | 18.45| 68.16 | 0.29 | Erection labor. | 20.83| 76.92 | 0.33 | Removal labor. | 12.16| 44.59 | 0.19 | Total labor. | 32.99| 121.51 | 0.52 | Total. | 51.44| 189.67 | 0.81 | | | |

    |GRAND TOTAL. | | |

    |Lumber in feet, B. M. |1,080 | 3,988 | 17.1 |Cost, in dollars. | | | | Lumber. | 46.45| 171.54 | 0.73 | Labor. | 62.78| 231.50 | 0.99 | Total. | 109.23| 403.04 | 1.72 +=============================+========+============+=========

    TABLE 10.--TIMBERING:--DETAILED COST OF TIMBER, LABOR, AND

    SUPERINTENDENCE. ROCK TUNNEL EXCAVATION UNDER 32D STREET, EAST OF

    CUT-AND-COVER SECTION.

    +====+=======+======================================+====================+

    | | | | EXCAVATION | |

    | | | TIMBER USED, IN | IN CUBIC | COST OF |

    | | | FEET, B. M. | YARDS | TIMBER |

    | | |------------------------+-------------+--------------------+ | | | Main |Blocking| Total | | Paid | | | | | |Date |timber.|timber. |timber.|Actual| for. | Main |Block.|Total.| | |-------+-------+--------+-------+------+------+------+------+------+ | |1907 | a | b | c | d | e | f | g | h | | |-------+-------+--------+-------+------+------+------+------+------+ |Ke|May | 18,016| 15,234 | 33,250| 1,736| 1,664| $810| $565|$1,375| | |June | 14,048| 11,528 | 25,576| 809| 698| 680| 457| 1,087| | |July | 20,092| 7,339 | 27,431| 1,022| 960| 900| 300| 1,200| | |August | 6,485| 2,632 | 9,117| 743| 716| 290| 110| 400| | |Sept. | 1,632| 2,224 | 3,856| 238| 238| 73| 94| 167| | |Removal| | | | | | | | | | |-------+-------+--------+-------+------+------+------+------+------+ | |Total | 60,273| 38,957 | 99,230| 4,548| 4,276|$2,703|$1,526|$4,229| |----+-------+-------+--------+-------+------+------+------+------+------+ |Ki|May | | 3,537 | 3,537| 614| 527| | $150| $150| | |June | 300| | 300| 357| 259| $14| | 14| | |July | 7,776| 5,811 | 13,587| 530| 404| 350| 233| 583| | |August | 19,712| 5,702 | 25,414| 925| 890| 887| 220| 1,107| | |Sept. | 20,556| 9,218 | 29,774| 1,585| 1,501| 925| 325| 1,250| | |Removal| | | | 1,669| 1,407| | | | | |-------+-------+--------+-------+------+------+------+------+------+ | |Total | 48,344| 24,268 | 72,612| 5,680| 4,988|$2,176| $928|$3,104| |----+-------+-------+--------+-------+------+------+------+------+------+ |Ko|May | 4,332| 8,788 | 13,120| 250| 188| $175| $366| $561| | |June | 7,132| 10,017 | 17,149| 496| 347| 324| 396| 720| | |July | 3,070| 200 | 3,270| 626| 606| 134| 10| 144| | |August | 10,704| 2,102 | 12,806| 718| 709| 481| 80| 561| | |Sept. | 2,400| 245 | 2,645| 396| 324| 108| 8| 116| | |Removal| | | | 209| 211| | | | |----|-------+-------+--------+-------+------+------+------+------+------+ | |Total | 27,638| 21,352 |48,990 | 2,695| 2,385|$1,242| $860|$2,102| |----|-------+-------+--------+-------+------+------+------+------+------+ | |Grand |136,255| 84,577 |220,832|12,923|11,649|$6,121|$3,314|$9,435| | |total | | | | | | | | | +====+=======+=======+========+=======+======+======+======+======+======+

    +====+=======+=======+=======+=======+=======+======+=======+=====+=====|

    | | | | | COST PER | COST PER |

    | | | | | CUBIC YARD | CUBIC YARD |

    | | |COST OF| TOTAL | (ACTUAL). | (PAID FOR). |

    | | | Labor | Cost. |-------+-------+------+-------+-----+-----+ | |DATE | | |Timber.|Labor. |Total.|Timber.|Labor|Total| | |-------+-------+-------+-------+-------+------+-------+-----+-----+ | | | | | h | i | j | h | i | j | | | | | | --- | --- | --- | --- | --- | --- | | |1907 | i | j | d | d | d | e | e | e | |----+-------+-------+-------+-------+-------+------+-------+-----+-----+ |Ke|May | $1,792| $3,167| $0.79 | $1.03 | $1.82| $0.82 |$1.07|$1.90| | |June | 1,576| 2,663| 1.34 | 1.95 | 3.29| 1.55 | 2.25| 3.81| | |July | 1,580| 2,780| 1.16 | 1.55 | 2.72| 1.25 | 1.64| 2.89| | |August | 300| 700| 0.53 | 0.40 | 0.94| 0.57 | 0.41| 0.98| | |Sept. | 60| 227| 0.70 | 0.25 | 0.95| 0.70 | 0.25| 0.95| | |Removal| 663| 663| | | | | | | | |-------+-------+-------+-------+-------+------+-------+-----+-----+ | |Total | $5,971|$10,200| $0.91 | $1.51 | $2.22| $1.00 |$1.40|$2.40| |----+-------+-------+-------+-------+-------+------+-------+-----+-----+ |Ki|May | $100| $250| $0.24 | $0.16 | $0.40| $0.28 |$0.19|$0.47| | |June | 44| 58| 0.04 | 0.12 | 0.16| 0.05 | 0.17| 0.22| | |July | 525| 7,108| 1.10 | 0.99 | 2.09| 1.44 | 1.30| 2.74| | |August | 1,018| 2,125| 1.20 | 1.10 | 2.30| 1.24 | 1.14| 2.38| | |Sept. | 1,028| 2,278| 0.79 | 0.65 | 1.44| 0.83 | 0.68| 1.51| | |Removal| 1,139| 1,139| | 0.68 | 0.68| | 0.81| 0.81| | |-------+-------+-------+-------+-------+------+-------+-----+-----+ | |Total | $3,854| $6,958| $0.55 | $0.68 | $1.23| $0.63 |$0.77|$1.40| |----+-------+-------+-------+-------+-------+------+-------+-----+-----+ |Ko|May | $303| $864| $2.24 | $1.21 | $3.45| $3.00 |$1.61|$4.61| | |June | 562| 1,282| 1.45 | 1.18 | 2.58| 2.07 | 1.61| 3.68| | |July | 156| 300| 0.23 | 0.25 | 0.48| 0.23 | 0.26| 0.49| | |August | 727| 1,288| 0.78 | 1.01 | 1.79| 0.80 | 1.02| 1.82| | |Sept. | 400| 516| 0.29 | 1.01 | 1.30| 0.36 | 1.23| 1.59| | |Removal| 535| 535| | 2.56 | 2.56| | 2.54| 2.54| | |-------+-------+-------+-------+-------+------+-------+-----+-----+ | |Total | $2,683| $4,785| $0.78 | $1.00 | $1.78| $0.88 |$1.12|$2.00| |----+-------+-------+-------+-------+-------+------+-------+-----+-----+ | |Grand |$12,508|$21,943| $0.73 | $0.97 | $1.70| $0.81 |$1.07|$1.88| | |total | | | | | | | | | +====+=======+=======+=======+=======+=======+======+=======+=====+=====+

    +====+===========+======================+

    | | | COST, PER 1,000 |

    | | | FT., B. M., OF |

    | | | TOTAL TIMBER. |

    | | |-------+------+-------| | | | Total | | | | | Date |timber.|Labor.|Total. | | |-----------+-------+------+-------| | | | h | i | j | | | | --- | --- | --- | | | 1907 | c | c | c | |----+-----------+-------+------+-------| |Ke|May |$41.35 |$53.89| $95.24| | |June | 42.50 | 61.62| 104.12| | |July | 43.74 | 57.60| 101.34| | |August | 43.87 | 32.90| 76.77| | |Sept. | 43.31 | 15.56| 58.87| | |Removal | | | | | |-----------+-------+------+-------| | |Total |$42.62 |$60.19|$102.81| |----+-----------+-------+------+-------| |Ki|May |$42.41 |$28.27| $70.68| | |June | 46.66 |146.33| 193.33| | |July | 42.91 | 38.64| 81.54| | |August | 43.56 | 40.06| 83.61| | |Sept. | 41.98 | 34.53| 76.51| | |Removal | | | | | |-----------+-------+------+-------| | |Total |$42.75 |$53.09| $95.84| |----+-----------+-------+------+-------| |Ko|May |$42.76 |$23.10| $65.86| | |June | 41.98 | 32.77| 74.75| | |July | 44.04 | 47.70| 91.74| | |August | 43.80 | 56.77| 100.57| | |Sept. | 43.85 |151.23| 195.08| | |Removal | | | | | |-----------+-------+------+-------| | |Total |$42.91 |$54.75| $97.65| |----+-----------+-------+------+-------| | |Grand total|$42.73 |$56.65| $99.38| +====+===========+=======+======+=======+

    Work was begun on September 1st, 1904, immediately on the completion of the work on the shaft. The North and South Tunnels in this case are completely independent, as will be seen from Plate XXXIV. The procedure adopted was to drive a top heading on the center line of each tunnel and to break down the bench from this. The drilling was at first supplied with steam power from a temporary plant, as the contractor was at that time installing his permanent plant, which was finished at the end of November, 1904. At this time the rate of advance averaged 3½ lin. ft. of full section per day of 24 hours.

    By the end of January the Weehawken rock tunnels were completely excavated, and by the middle of April, 1905, the excavation for the shield chambers was finished; the erection of the shields was started at the end of that month.

    TABLE 11.

    +=========+========+=============+========+

    Grade. |Total No.|Rate per|Drilling and |Mucking:|Timbering:
    | | day. |blasting: No.| No. | No.
    ------------------+---------+--------+-------------+--------+----------
    Superintendent | 1 | $7.70 | ½ | 1/8 | 3/8
    Assistant engineer| 1 | 5.80 | ½ | 1/8 | 3/8
    Electrician | 1 | 3.50 | ½ | 1/8 | 3/8
    Engineer | 1 | 3.50 | | 1 |
    Signalman | 1 | 2.00 | | 1 |
    Foreman | 3 | 4.00 | 1 | 1 | 1
    Driller | 5 | 3.00 | 5 | |
    Driller's helper | 5 | 2.00 | 5 | |
    Laborers | 14 | 2.00 | | 14 |
    Timbermen | 3 | 3.00 | | | 3
    " helpers | 4 | 2.00 | | | 4
    Machinist | 1 | 4.00 | 1 | |
    Blacksmith | 2 | 3.50 | 2 | |
    " helper | 2 | 2.00 | 2 | |
    Nipper | 2 | 2.00 | 2 | |
    Waterboy | 1 | 2.00 | 1 | |
    ------------------+---------+--------+-------------+--------+---------
    Total | 47 | | 20½ | 17-3/8 | 9-1/8
    ## +=========+========+=============+========+

    The general scheme of excavation is shown by Plate XXXIII. The bench was kept 50 or 60 ft. behind the face of the heading. The powder used was 60% Forcite. The general system of drilling was as shown in Fig. 7. The average length of hole drilled per cubic yard of excavation was 2.9 ft., as against 7.70 ft. at Manhattan; and the amount of powder used was 1.96 lb. per cu. yd., as against 1.24 lb. at Manhattan. There was little timbering. A length of about 30 or 40 ft. adjoining the Weehawken shaft was timbered, and also a shattered seam of about 17 ft. in width between Stations 262 + 10 and 262 + 27.

    [Illustration: LAND TUNNELS TYPICAL METHOD OF DRILLING USED IN THE

    WEEHAWKEN TUNNELS FIG. 7]

    The two entirely separate tunnels gave a cross-section which was much more easily timbered than the wide flat span at Manhattan, and the segmental timbering was amply strong without posts or other reinforcement.

    Table 12 is a summary of the cost of excavating the Land Tunnels, based on actual records carefully kept throughout the work.

    TABLE 12.--COST OF EXCAVATION OF LAND TUNNELS, IN DOLLARS PER CUBIC

    YARD.

    +=========+=========+

    | | |Total yardage
    | | | and
    |Manhattan|Weehawken|average cost.
    --------------------------------------+---------+---------+-------------
    Cubic yards excavated |43,289 | 8,311 | 51,600
    Labor. | | |
    Surface transport | $0.49| $0.87| $0.55
    Drilling and blasting | 2.37| 1.55| 2.24
    Mucking | 2.49| 2.08| 2.42
    Timbering | 0.87| 0.18| 0.76
    --------------------------------------+---------+---------+-------------
    Total labor | $6.22| $4.68| $5.97
    --------------------------------------+---------+---------+-------------
    Material. | | |
    Drilling | $0.15| $0.15| $0.15
    Blasting | 0.21| 0.21| 0.21
    Timber | 0.39| 0.20| 0.36
    --------------------------------------+---------+---------+-------------
    Total material | $0.75| $0.56| $0.72
    --------------------------------------+---------+---------+-------------
    Plant running | $0.76| $0.65| $0.74
    Surface labor, repairs and maintenance| 0.15| 0.08| 0.14
    Field office administration | 1.05| 1.18| 1.07
    --------------------------------------+---------+---------+-------------
    Total field charges | $8.96| $7.15| $8.64
    --------------------------------------+---------+---------+-------------
    Chief office administration | $0.34| $0.38| $0.34
    Plant depreciation | 0.66| 1.01| 0.72
    Street and building repairs | 0.27| | 0.23
    --------------------------------------+---------+---------+-------------
    Total average cost per cubic yard | $10.23| $8.54| $9.93
    ## +=========+=========+

    Masonry Lining of Land Tunnels.

    Plates XXXII and XXXIV show in detail the tunnels as they were actually built. It will be seen that in all work, except in the Gy-East contract, there was a bench at each side of each tunnel in which the cable conduits were embedded. In Gy-East the bank of ducts which came next to the middle wall was carried below subgrade, and the inner benches were omitted.

    The side-walls and subgrade electric conduits were water-proofed with felt and pitch. The water-proofing was placed on the outside of the side-walls (that is, on the neat line), and the space between the rock and the water-proofing was filled with concrete. This concrete was called the "Sand-Wall."

    The general sequence of building the masonry lining is shown in Fig. 8.

    The operations were as follows:

    1.--Laying concrete for the whole height of the
    sand-walls, and for the floor and foundations for
    walls and benches up to the level of the base of
    the conduits;

    2.--Water-proofing the side-walls, and, where there was
    a middle trench containing subgrade conduits,
    laying and water-proofing these conduits;

    3.--Building concrete wall for conduits to be laid
    against, and, where there was a middle trench,
    filling up with concrete between the conduits;

    4.--Laying conduits;

    5.--Laying concrete for benches and middle-wall;

    6.--Building haunches from top of bench to springing of
    brick arch;

    7.--Building brick arch and part of concrete
    back-filling;

    8.--Finishing back-filling.

    The whole work will be generally described under the headings of Concrete, Brickwork, Water-proofing, and Electric Conduits.

    Concrete.--The number of types and the obstructions caused by the heavy posting of the timbering made it inadvisable to use built-up traveling forms at the Manhattan side, though they were used in the Weehawken Rock Tunnels.

    The specifications required a facing mixture of mortar to be deposited against the forms simultaneously with the placing of the concrete. This facing mixture was dry, about 2 in. thick, and was kept separate from the concrete during the placing by a steel diaphragm. The diaphragm was removed when the concrete reached the top of each successive layer, and the facing mixture and concrete were then tamped down together. This method was at first followed and gave good results, which was indeed a foregone conclusion, as the Weehawken shaft had been built in this way.

    However, it was found that as good results, in the way of smooth finish, were to be obtained without the facing mixture by spading the concrete back from the forms, so that the stone was forced back and the finer portion of the mixture came against the forms; this method was followed for the rest of the work. All corners were rounded off on a 1-in. radius by mouldings tacked to the forms. The side-bench forms were used about four times, and were carefully scraped, planed, filled at open joints, and oiled with soap grease each time they were set up. When too rough for face work they were used for sand-wall and other rough work.

    The mixing was done by a No. 4 Ransome mixer, driven by 30-h.p. electric motors. The mixer at Manhattan was set on an elevated platform at the north end of the intercepting arch; that at Weehawken was placed at the entrance to the tunnels. The sand and stone were stored in bins above the mixers, and were led to the hoppers of the mixers through chutes.

    The hoppers were divided into two sections, which gave the correct quantities of sand and stone, respectively, for one batch. The water was measured in a small tank alongside. A "four-bag" batch was the amount mixed at one time, that is, it consisted of 4 bags of cement, 8¾ cu. ft. of sand, and 17½ cu. ft. of broken stone, and was called a 1 : 2½ : 5 mixture. It measured when mixed about ¾ cu. yd.

    The cement was furnished to the contractor by the Railroad Company, which undertook all the purchasing from the manufacturer, as well as the sampling, testing, and storing until the contractor needed it. The Railroad Company charged the contractor $2 a barrel for this material.

    The sand was required by the specifications to be coarse, sharp, and silicious, and to contain not more than 0.5% of mica, loam, dirt, or clay. All sand was carefully tested before being used. The stone was to be a sound trap or limestone, passing a 1½-in. mesh and being retained on 3/8-in. mesh. The contractor was allowed to use a coarser stone than this, namely, one that had passed a 2-in. and was retained on a 1½-in. mesh.

    The concrete was to be machine-mixed, except in cases of local necessity. The quantity of water used in the mixture was to be such that the concrete would quake on being deposited, but the engineer was to use his discretion on this point. Concrete was to be deposited in such a manner that the aggregates would not separate. It was to be laid in layers, not exceeding 9 in. in thickness, and thoroughly rammed. When placing was suspended, a joint was to be formed in a manner satisfactory to the engineer. Before depositing fresh concrete, the entire surface on which it was to be laid was to be cleaned, washed and brushed, and slushed over with neat cement grout.

    Concrete which had begun to set was not to be used, and retempering was not to be allowed.

    [Illustration: MANHATTAN TYPES FIG. 8.]

    The forms were to be substantial and hold their shape until the concrete had set. The face forms were to be of matched and dressed planking, finished to true lines and surfaces; adequate measures were to be taken to prevent concrete from adhering to the forms. Warped or distorted forms were to be replaced. Plastering the face was not allowed. Rock surfaces were to be thoroughly washed and cleaned before the concrete was deposited.

    These specifications were followed quite closely.

    A typical working gang, as divided among the various operations, is shown below:

    Superintendence.
    ½ Superintendent @ $250 per month
    ½ Assistant engineer " 150 " "
    1 Assistant superintendent " 150 " "
    Surface Transport.
    1 Foreman @ $2.50 per day
    1 Engineer " 3.00 " "
    1 Signalman " 2.00 " "
    16 Laborers " 1.75 " "
    3 Teams " 7.50 " "
    Laying.
    1 Foreman @ $4.00 per day
    8 Laborers " 2.00 " "
    Forms.
    1 Foreman @ $4.50 per day
    4 Carpenters " 3.25 " "
    5 Helpers " 2.25 " "
    Tunnel Transport.
    ¼ Foreman @ $3.25 per day
    ¼ Engineer " 3.00 " "
    ¼ Signalman " 2.00 " "
    4 Laborers " 1.75 " "
    Mixers.
    ¼ Foreman @ $3.25 per day
    2 Laborers " 1.75 " "

    The superintendent and assistant engineer looked after the brickwork and other work as well as the concrete. The surface transport gang handled all the materials on the surface, including the fetching of the cement from the cement warehouses.

    The tunnel transport gang handled all materials in the tunnel, but, when the haul became too long, the gang was reinforced with laborers from the laying gang. Of the laying gang, two generally did the spading, two the spreading and tamping, and the remaining force dumped the concrete. The general cost of this part of the work is shown in Table 13.

    The figures in Table 13 include the various items built into the concrete and some that are certificate extras in connection with the concrete, such as drains, ironwork and iron materials, rods and bars, expanded metal, doors, frames and fittings, etc.

    Water-proofing.--According to the specifications, the water-proofing was to consist of seven layers of pitch and six layers of felt on the side-walls and a ½-in. layer of mastic, composed of coal-tar and Portland cement, to be plastered over the outside of the arches.

    By the time the work was in hand, some distrust had arisen as to the efficiency of this mastic coating, and a great deal of study was devoted to the problem of how to apply a felt and pitch water-proofing to the arches. The difficulty was that there was no room between the rock and the arch or between the timber and the arch (as the case might be) in which to work.

    Several ingenious schemes of putting the felt on in layers, or in small pieces like shingles, were proposed and discussed, and a full-sized model of the tunnel arch was even built on which to try experiments, but it was finally decided to overcome the difficulty by leaving out the arch water-proofing altogether, and simply building in pipes for grouting through under pressure, in case it was found that the arch was wet.

    As to the arch built through the length excavated by cut-and-cover on the New York side, it was resolved to water-proof that with felt and pitch exactly as the side-walls were done, the spandrel filling between the arches being raised in a slight ridge along the concrete line between tunnels in order to throw the water over to the sides. The portions of arch not water-proofed were rather wet, and grouting with a 1:1 mixture was done, but only with the effect of stopping large local leaks and distributing a general dampness over the whole surface of the arch.

    TABLE 13.--COST OF CONCRETE IN LAND TUNNELS, IN DOLLARS PER CUBIC YARD.

    +==========+==========+

    | | | Total
    |Manhattan.|Weehawken.| yardage.
    ---------------------------------------+----------+----------+----------
    Cubic yards placed |14,706½ | 3,723 |18,429½
    ---------------------------------------+----------+----------+----------
    LABOR. | Average Cost per Cubic Yard.
    ---------------------------------------+----------+----------+----------
    Surface transport | $0.31 | $1.43 | $0.54
    Superintendence and general labor at | | |
    point of work | 0.31 | 1.31 | 0.51
    Mixing | 0.52 | 0.56 | 0.53
    Laying | 1.38 | 1.45 | 1.39
    Tunnel transport | 1.30 | 1.47 | 1.34
    Cleaning | 0.21 | | 0.17
    Forms: erecting and removal | 1.58 | 1.51 | 1.56
    ---------------------------------------+----------+----------+----------
    Total labor | $5.61 | $7.73 | $6.04
    ---------------------------------------+----------+----------+----------
    MATERIAL.
    ---------------------------------------+----------+----------+----------
    Cement | $2.30 | $2.22 | $2.28
    Sand | 0.34 | 0.40 | 0.36
    Stone | 0.91 | 0.61 | 0.85
    Lumber for forms | 0.47 | 0.45 | 0.47
    Sundry tunnel supplies | 0.16 | 0.17 | 0.16
    ---------------------------------------+----------+----------+----------
    Total materials | $4.18 | $3.85 | $4.12
    ---------------------------------------+----------+----------+----------
    Plant running | $0.44 | $0.44 | $0.44
    Surface labor, repairs and maintenance | 0.25 | 1.24 | 0.44
    Field office administration | 0.50 | 1.72 | 0.75
    ---------------------------------------+----------+----------+----------
    Total field charges | $10.98 | $14.98 | $11.79
    ---------------------------------------+----------+----------+----------
    Plant depreciation | $0.62 | $1.57 | $0.81
    Chief office administration | 0.24 | 0.31 | 0.25
    ---------------------------------------+----------+----------+----------
    Total average cost per cubic yard | $11.84 | $16.86 | $12.85
    ---------------------------------------+----------+----------+----------
    Cost of Miscellaneous Items in Concrete.
    ---------------------------------------+----------+----------+----------
    |Manhattan.|Weehawken.| Average.
    Cubic yards |14,706½ | 3,723 |18,429½
    Amount, in dollars |$6,184.83 | $1,756.79|$7,941.62
    Unit cost | 0.42 | 0.47| 0.43
    =======================================+==========+==========+==========

    The 24-ft. 6-in. tunnel adjoining the Terminal Station-West was water-proofed by a surface-rendering method which, up to the present time, has been satisfactory. Generally speaking, the arches of the Land Tunnels, though not dripping with water, are the dampest parts of the whole structure from Tenth Avenue to Weehawken, and it would seem as if some form of water-proofing over these arches would have been a distinct advantage.

    There was no difficulty in applying the water-proofing on the side-walls, after a little experience had been gained as to the best methods. The specifications required the sand-wall to be covered with alternate layers of coal-tar pitch and felt, seven layers of the former and six layers of the latter, the felt to be of Hydrex brand or other equally satisfactory to the engineer.

    The pitch was to be straight-run, coal-tar pitch which would soften at 60° Fahr., and melt at 100° Fahr., being a grade in which distillate oils, distilled from it, should have a specified gravity of 1.105. The pitch was to be mopped on the surface to a uniform thickness of 1/16 in., and a covering of felt, previously mopped with pitch, was to be applied immediately. The sheets were to lap not less than 4 in. on cross-joints and 12 in. on longitudinal joints, and had to adhere firmly to the pitch-covered surface.

    This layer was then to be mopped, and another layer placed, and so on until all the layers were in place. This water-proofing was to extend from the bottom of the cable conduits to the springing of the brick arch. Where sub-track conduits were used, these were to be surrounded with their own water-proofing. The work was carried out as specified; the sand-walls were not rendered, but were built smooth enough to apply the water-proofing directly to them.

    They were dried with gasoline torches before the application of the pitch, and in very wet sections grooves were cut to lead the water away.

    The first attempts were with the felt laid in horizontal strips. This ended very disastrously, as the pitch could not sustain the weight of the felt, and the whole arrangement slipped down the wall. The felt was then laid vertically, being tacked to a piece of horizontal scantling at the top of the sand-wall and also held by a row of planks braced against it at about half its height. A layer of porous brick was laid as a drain along the base of the water-proofing, covered by a single layer of felt to prevent it from becoming choked with concrete.

    The water-proofing of the sub-track conduits was troublesome, as the numerous layers and the necessity for preserving the proper laps in both directions between adjacent layers made the whole thing a kind of Chinese puzzle. Various modifications, to suit local conditions, were made from time to time. Conduits outside the general outline of the tunnel are difficult to excavate, to lay, and to water-proof, and should be avoided wherever possible.

    The usual force in water-proofing consisted of a foreman, at $3.50 per day, and nine laborers at $1.75 per day. These men not only laid the water-proofing, but transported the materials, heated the pitch, and cut up the rolls of felt. In general, two men transported material, one tended the heater, and the other six worked in pairs, two preparing the surface of the concrete sand-wall, two laying pitch, and two laying felt.

    The cost of the water-proofing operation was about as shown in Table 14.

    TABLE 14.--COST OF WATER-PROOFING, IN DOLLARS PER SQUARE FOOT.

    +==========+===========+

    |Manhattan.| Weehawken.| Total.
    ---------------------------------------+----------+-----------+--------
    Square feet covered | 47,042 | 13,964 | 60,736
    ---------------------------------------+----------+-----------+--------
    Average cost per square foot.
    ---------------------------------------+----------+-----------+--------
    Labor | $0.07 | $0.07 | $0.07
    Material | 0.12 | 0.09 | 0.11
    ---------------------------------------+----------+-----------+--------
    Total field charges | $0.19 | $0.16 | $0.18
    Chief office and plant depreciation | 0.01 | 0.03 | 0.02
    ---------------------------------------+----------+-----------+--------
    Total average cost | $0.20 | $0.19 | $0.20
    ## +==========+===========+

    Brickwork in Arches.--Owing to the heavy timbering, the brickwork at Manhattan was interfered with to a considerable extent, and the gang was always kept at work at two or more places. The work was carried up to a point where it was necessary to back-fill, or prop or cut away encroaching timbers, and then the men were moved to another place while this was being done.

    The centers were set up in sets of seven, spaced 4 ft. apart. Two 14-ft. lengths of 3 by 4-in. yellow pine lagging were used with each set of ribs, with 24 by 8-in. block lagging in the crown.

    All centers were set ¼ in. high, to allow for settlement, except in the 24-ft. 6-in. span, in which they were set ½ in. high. This proved ample, the average settlement of the ribs being 0.01 ft. and of the masonry, 0.003 ft. In the 24-ft. 6-in. span the ribs were strengthened with 6 by 6-in. blocking and 12 by 12-in. posts to subgrade. Great trouble was here encountered with encroaching timbering, due to the settlement of the wide flat span. Grout pipes were built in, as previously mentioned.

    Each mason laid an average of 0.535 cu. yd. of brickwork per hour, or 4.28 cu. yd. per day. The number of bricks laid per mason per hour was 218, or 1,744 per day.

    The bricks were of the best quality of vitrified paving brick, and were obtained from the Jamestown Brick Company, of Jamestown, N. Y. The average size was 8¾ by 3-15/16 by 2-7/16 in.; the average number per cubic yard of masonry was 408, the arches being from 19 ft. to 24 ft. 6 in. in span and from 22 to 27 in. thick. The joints were 3/16 in. at the face and averaged 9/16 in. through the arch.

    The proportions for mortar were 1 of cement and 2½ of sand. One cubic yard of masonry was composed of 73.5% brick and 26.5% mortar. The volume of the ingredients in a four-bag batch was 12.12 cu. ft., and the resulting mixture was 9.54 cu. ft. The number of barrels of cement was 0.915 per cu. yd. of masonry, and about 17.7% of the mortar made was wasted. The average force employed was:

    Laying.
    1 Foreman @ $8.00 per day
    4 Layers " 6.00 " "
    8 Tenders " 2.00 " "
    2 Mixers " 2.00 " "
    Forms.
    1 Foreman @ $4.50 per day
    4 Carpenters " 3.50 " "
    5 Helpers " 2.25 " "
    Transport.
    ¼ Hoist engineer @ $3.00 per day
    ¼ Signalman " 2.00 " "
    4 Laborers " 2.00 " "

    For materials, the following prices prevailed:

    Cement, $2.00 per bbl.,
    Sand, $0.90 to $1.00 per cu. yd.,
    Brick, $16.00 per thousand, delivered at yard,
    Centers, $26.00 each,
    Lagging, $45.00 per 1,000 ft. B. M.

    The cost of the brickwork is given in Table 15.

    TABLE 15.--COST OF BRICKWORK.

    +==========+==========+

    |Manhattan.|Weehawken.|Total.
    -------------------------------------------+----------+----------+------
    Cubic yards placed | 4,137 | 790 |4,927
    -------------------------------------------+----------+----------+------
    LABOR. |Average Cost per Cubic Yard.
    -------------------------------------------+----------+----------+------
    Surface transport | $0.35 | $1.19 | $0.48
    Superintendent and general labor at point | | |
    of work | 0.17 | 0.04 | 0.16
    Laying and mixing | 2.58 | 3.20 | 2.60
    Forms: erection and removal | 2.62 | 0.32 | 2.25
    Tunnel transport | 1.19 | 1.12 | 1.18
    -------------------------------------------+----------+----------+------
    Total labor | $6.91 | $5.87 | $6.75
    -------------------------------------------+----------+----------+------
    MATERIAL.
    -------------------------------------------+----------+----------+------
    Brick | $6.56 | $6.56 | $6.56
    Cement | 1.76 | 1.75 | 1.76
    Sand | 0.20 | 0.28 | 0.22
    Forms | 0.92 | 0.98 | 0.98
    Overhead conductor pockets | 0.15 | 0.09 | 0.13
    -------------------------------------------+----------+----------+------
    Total material | $9.59 | $9.66 | $9.60
    -------------------------------------------+----------+----------+------
    Plant running | $0.55 | $0.30 | $0.51
    Surface labor, repairs and maintenance | 0.36 | 1.30 | 0.51
    Field office administration | 0.55 | 0.88 | 0.60
    -------------------------------------------+----------+----------+------
    Total field charges | $17.96 | $18.01 |$17.97
    -------------------------------------------+----------+----------+------
    Chief office administration | $0.60 | $0.66 | $0.61
    Plant depreciation | 0.35 | 0.64 | 0.39
    -------------------------------------------+----------+----------+------
    Total average cost per cubic yard | $18.91 | $19.31 |$18.97
    ===========================================+==========+==========+======

    In Table 16 the cost of grout is expressed in terms of barrels of cement used, because in the schedule of prices attached to the contract, that was the unit of payment for grout.

    TABLE 16.--COST OF GROUT OVER ARCHES IN LAND TUNNELS.

    Cost, in Dollars per Barrel of Cement Used.

    +===============+==========+

    | Manhattan. | |
    |(Gy-East only.)|Weehawken.|Total.
    --------------------------------------+---------------+----------+------
    Barrels used | 3,000½ | 261½ |3,262
    --------------------------------------+---------------+----------+------
    Average Cost
    per Barrel of Cement Used.
    --------------------------------------+---------------+----------+------
    Labor | $0.55 | $0.46 |$0.53
    Material | 2.30 | 2.25 | 2.28
    Field office administration | 0.08 | 0.06 | 0.08
    Plant and supplies | 0.10 | 0.07 | 0.09
    --------------------------------------+---------------+----------+------
    Total field charges | $3.03 | $2.84 |$2.98
    --------------------------------------+---------------+----------+------
    Chief office and plant depreciation | 0.21 | 0.22 | 0.28
    --------------------------------------+---------------+----------+------
    Total average cost | $3.24 | $3.06 |$3.20
    ## +===============+==========+

    Vitrified Earthenware Conduits for Electric Cables.--The general drawings will show how the ducts were arranged, and that manholes were provided at intervals. They were water-proofed, in the case of those embedded in the bench, by the general water-proofing of the tunnels, which was carried down to the level of the bottom of the banks of ducts; and in the case of those below subgrade, by a special water-proofing of felt and pitch wrapped around the ducts themselves.

    The portion of wall in front of the ducts was bonded to that behind by bonds, mostly of expanded metal, passing between the ducts. Examples of the bonding will be seen in the drawings.

    The joints between successive lengths of 4-way and 2-way ducts were wrapped with two thicknesses of cotton duck, 6 in. wide, those of single-way ducts were not wrapped, but plastered with cement mortar. The ducts were laid on beds of mortar, and were made to break joints at top and bottom and side to side with the adjacent ducts. They were laid with a wooden mandrel; a square leather washer at the near end acted as a cleanser when the mandrel was pulled through.

    The specifications required the ducts to be laid at the same time as the concrete and be carried up with it, but this was found to be a very awkward operation, as the tamping of the concrete and the walking of men disturbed the ducts, especially as the bonds lay across them. It was resolved, therefore, to build the portion of the wall behind the ducts first, with the bonds embedded in it at the proper heights and projecting from it, then to lay up the banks of ducts against this wall, bending the bonds down as they were reached, and finally, after all the ducts were in, to lay the concrete in front of and over the top of the ducts.

    Several detailed modifications of this general scheme were followed at one time or another when necessary or advisable.

    The laying of ducts below subgrade was not complicated by the presence of bonds, the water-proofing caused the trouble here, as before described.

    The specifications called for a final rodding after completion. A group of the apparatus used in this process is shown in Fig. 1, Plate XXXV; the various parts are identified by the following key:

    KEY TO FIG. 1, PLATE XXXV.

    1.--4-way duct, for telephone and telegraph cables,
    2.--2-way duct, for telephone and telegraph cables,
    3.--1-way duct, for high- and low-tension cables,
    4.--Plug for closing open ends of ducts,
    5.--Plug for closing open ends of ducts in position,
    6, 7, and 8.--Cutters for removing obstructions,
    9.--Hedgehog cutter for removing grout in ducts,
    10.--Rodding mandrel for multiple ducts,
    11.--Laying mandrel,
    12.--Rodding mandrel, with jar-link attached,
    13.--Laying mandrel,
    14 and 15.--Rubber-disk cleaners, used after final
    rodding,
    16 and 17.--Sectional wooden rods used for rodding,
    18.--Section of iron rods used for rodding,
    19.--Jar-link,
    20.--Cotton duck for wrapping joints of multiple ducts,
    21.--Hook for pulling forward laying mandrel,
    22.--Top view of trap for recovering lost or broken
    rods left in ducts.

    [Illustration: PLATE XXXV. TRANS. AM. SOC. CIV. ENGRS. VOL. LXVIII, No.

    1155. HEWETT AND BROWN ON PENNSYLVANIA R. R. TUNNELS: NORTH RIVER

    TUNNELS. FIG. 1. FIG. 2.]

    Ordinary ¾-in. gas pipe was used for the rod, and a cutter with rectangular cross-section and rounded corners was run through ahead of the mandrel: following the cutter came a scraper consisting of several square leather washers, of the size of the ducts, spaced at intervals on a short rod. The mandrel itself was next put through, three or four men being used on the rods. All the ducts in a bank were thus rodded from manhole to manhole. When a duct was rodded it was plugged at each end with a wooden plug. A solid wooden paraffined plug was used at first, but afterward an expansion plug was used.

    Very little trouble was met in rodding the power conduits, except for a few misplaced ducts, or a small mound of mortar or a laying mandrel left in. At such points a cut was made in the concrete and the duct replaced.

    In the subgrade telephone and telegraph ducts east of the Manhattan Shaft, much trouble was caused by grout in the ducts. The mandrel and cutters were deflected and broke through the web of the ducts rather than remove this hard grout. Trenches had to be cut from the floor to the top of the water-proofing, the latter was then cut and folded back, and the ducts replaced. To do this, a number of ducts had to be taken out to replace the broken ones and get the proper laps. The water-proofing was then patched and the concrete replaced. This grout had not penetrated the water-proofing, but had got in through the ends of the ducts where they had not been properly plugged and protected.

    The duct gang, both for laying and rodding, generally consisted of

    1 Foreman, at $3.50 per day,
    and 9 laborers, at $1.75 per day.

    When laying: 4 men were laying, 2 men mixing and carrying mortar, and 3 were transporting material. When rodding: 4 men were rodding, 2 men at adjacent manholes were connecting and disconnecting cutters and mandrels, 1 was joining up rods, and 2 men assisting generally.

    The cost of this work is shown in Table 17.

    Transportation and Disposal.

    The track on the surface and in the tunnels was of 20-lb. rails on a 2-ft. gauge.

    The excavation was handled in scale-boxes carried on flat cars, and the concrete in 1¼-cu. yd. mining cars dumping either at the side or end.

    TABLE 17.--COST OF CONDUIT WORK.

    +==========+==========+

    |Manhattan.|Weehawken.| Total.
    -----------------------------------------+----------+----------+-------
    Duct feet | 115,962 | 35,155 |151,117
    -----------------------------------------+----------+----------+-------
    Average Cost per Duct Foot.
    -----------------------------------------+----------+----------+-------
    Labor | $0.035 | $0.032 | $0.034
    Material | 0.043 | 0.052 | 0.045
    -----------------------------------------+----------+----------+-------
    Total field charges | 0.078 | 0.084 | 0.079
    -----------------------------------------+----------+----------+-------
    Chief office and plant depreciation | 0.005 | 0.008 | 0.006
    -----------------------------------------+----------+----------+-------
    Total average cost | $0.083 | $0.092 | $0.085
    ## +==========+==========+

    When the haulage was up grade, 6 by 6-in. Lidgerwood hoisting engines, with 10-in. single friction drums, and driven by compressed air from the high-pressure lines, were used. Down grade, cars were moved and controlled by hand.

    The muck which came through the shaft at Manhattan was dumped into hopper bins on the surface and thence loaded into trucks at convenience.

    At the open cut, the muck was dumped into trucks direct. The trucking was sublet by the contractor to a sub-contractor, who provided trucks, teams, and trimmers at the pier. At Weehawken, arrangements were made with the Erie Railroad which undertook to take muck which was needed as fill. The tunnel cars, therefore, were dumped directly on flat cars which were brought up to a roughly made platform near the shaft.

    The hoisting at Manhattan was by derrick at Tenth Avenue and the open cut, and by the elevator at the Manhattan Shaft. At Weehawken, all hoisting was done by the elevator in the shaft.

    The sand and stone were received at the wharves by scows. At Manhattan, these materials were unloaded on trucks by an overhead traveler, and teamed to the shaft, where they were unloaded by derricks into the bins.

    At Weehawken, they were unloaded by an orange-peel grab bucket, loaded into cars on the overhead trestle, transported in these to the top of the shaft, and discharged into the bins.

    The cement at Manhattan was trucked from the Company's warehouse, at Eleventh Avenue and 38th Street, to the shaft, where it was put into a supplementary storage shed at the top of the shaft, whence it was removed to the mixer by the elevator when needed. At Weehawken, it was taken on flat cars directly from the warehouse to the mixer.

    Lighting.

    Temporarily and for a short time at the start, kerosene flares were used for light until replaced by electric lights, the current for which was furnished by the contractor's generators, which have been described under the head of "Power Plant."

    The lamps used along the track were of 16 c.p., and were protected by wire screens; these were single, but, wherever work was going on, groups of four or five, provided with reflectors, were used.

    Pumping.

    Two pumps were installed at the Manhattan Shaft. They had to handle the water, not only from the rock tunnels, but also from those under the river. One was a Deane compound duplex pump, having a capacity of 500 gal. per min., the other, a Blake pump, of 150 gal. per min. They were first driven by steam direct from the power-house, but compressed air was used later. When the power-house was shut down, an electrically-driven centrifugal pump was used. This was driven by a General Electric shunt-wound motor, Type C-07½, with a speed of 1,250 rev. per min. at 250 volts and 37.5 amperes (10 h.p.) when open, and 22.9 amperes (6 h.p.) when closed, and had a capacity of 450 gal. per min.

    To send the water to the shaft sump during the construction, small compressed-air Cameron pumps, of about 140 gal. per min., were used.

    At the Weehawken shaft two pumps were used; these dealt with the water from the Bergen Hill Tunnels as well as that from the Weehawken Tunnels.

    At first a Worthington duplex pump having a capacity of about 500 gal. per min. was used. Later, this was replaced by a General Electric shunt-wound motor, Type O-15, with a speed of 925 rev. per min. at 230 volts and 74 amperes (20 h.p.) when open, and 38.5 amperes (10 h.p.) when closed. Its capacity was 240 gal. per min. During the progress of the construction, the water was pumped from the working face to the shaft by small Cameron pumps similar to those used at Manhattan. When the work was finished, a subgrade reversed-grade drain carried the water to the shaft sump by gravity.

    The work in the Manhattan Land Tunnels was practically finished by May 1st, 1908, though the ventilating arrangements and overhead platform in the intercepting arch were not put in until after the River Tunnel concrete was completed, so that the work was not finished until September, 1909.

    The Weehawken Land Tunnels work was finished in July, 1907, but the benches and ventilating arrangements in the Weehawken Shaft were not put in until after the completion of the Bergen Hill Tunnels, and so were not finished until August, 1909.

    The reinforced concrete wall around the Weehawken Shaft, together with the stairs from the bench level of the shaft to the surface, was let as a separate contract; the work was started on September 15th, 1909, and finished by the end of December, 1909.

    RIVER TUNNELS.

    The River Tunnel work, from some points of view, has the most interest.

    It is interesting because it is the first main line crossing of the formidable obstacle of the Hudson River, and also by reason of the long and anxiously discussed point as to whether, in view of the preceding experiences and failures to construct tunnels under that river, foundations were needed under these tunnels to keep them from changing in elevation under the action of heavy traffic.

    The River Tunnels here described start on the east side of the shield chambers on the New York side and end at the east side of the shield chambers on the New Jersey side. They thus include the New York and exclude the New Jersey shield chambers, the reason for such discrimination being that the New York shield chambers are lined with cast iron while those on the New Jersey side are of the typical rock section type, as already described. The design of the tunnels and their accessories will be first described, then will come the construction of the tunnels as far as the completion of the metal lining, followed by a description of the concrete lining and completion of the work.

    Design of Metal Lining.

    New York Shield Chambers.--The shield chambers may be seen on Plate XXXII, previously referred to, which shows the junction of the iron-lined tunnels and the shield chambers. They consist of two iron-lined pieces of tunnel placed side by side, with semi-circular arches and straight side-walls. The segments of the arch are made to break joint with one another by making the side-wall or column castings of two different heights, as shown in Fig. 9. The length of each ring is 18 in.

    The reason for the adoption of this type of construction was the necessity for keeping the width of the permanent structure within the 60-ft. width of the street. The length of this twin structure is 28.5 ft., and the weight of the metal in it is as follows:

    19 long-column arch rings at 22,802 lb. 433,238 lb.
    19 short-column arch rings at 23,028 lb. 437,532 "
    -------
    Total weight 870,770 lb.

    General Type of River Tunnel Lining.--The main ruling type adopted for the tunnels under the Hudson River, and in the soft water-bearing ground for some distance on the shoreward side of the river lines, consists of two parallel metal-lined tunnels, circular in cross-section, each tunnel being 23 ft. outside diameter, and the two tunnels 37 ft. apart from center to center, as shown on Fig. 10.

    The metal lining is of cast iron (except for a few short lengths of cast steel) and of the usual segmental type, consisting of "Rings" of iron, each ring being 2 ft. 6 in. in length, and divided by radial joints into eleven segments, or "Plates," with one "Key," or closing segment, having joints not radial but narrower at the outside circumference of the metal lining than at the inside. The whole structure is joined, segment to segment, and ring to ring, by mild-steel bolts passing through bolt holes in flanges of all four faces of each segment.

    The joints between the segments are made water-tight by a caulking of sal-ammoniac and iron borings driven into grooves formed for the purpose on the inner edges of the flanges. The clearances between the bolts and the bolt holes are also made water-tight by using grummets or rings of yarn smeared with red lead, having a snug fit over the shank of the bolt and placed below the washer on either end of each bolt.

    When passing through ground more or less self-sustaining, the space outside the iron lining (formed by the excavation being necessarily rather larger than the external diameter of the lining itself) was filled with grout of 1:1 Portland cement and sand forced by air pressure through grout holes in each segment. These holes were tapped, and were closed with a screw plug before and after grouting.

    [Illustration: DETAILS OF MANHATTAN SHIELD CHAMBERS FIG. 9.]

    Having thus stated in a general way the main ruling features of the design, a detailed description of the various modifications of the ruling type will be given.

    [Illustration: TYPICAL CROSS-SECTION OF RULING DESIGN OF METAL-LINED SHIELD-DRIVEN TUNNELS FIG. 10.]

    The two main divisions of the iron lining are the "ordinary" or lighter type and the heavy type. The details of the ordinary iron are shown in Fig. 11, which shows all types of lining. It was on this design that the contract was let, and it was originally intended that this should be the only type of iron used. The dimensions of the iron are clearly shown on the drawing, and it will be seen that the external diameter is 23 ft., the interior diameter, 21 ft. 2 in., the length of each ring, 2 ft. 6 in., and the thickness of the iron skin or web, 1½ in.

    The bolt holes in the circumferential flanges are evenly spaced through the circle, so that adjacent rings may be bolted together in any relative position as regards the radial joints, and, as a matter of fact, in the erection of the tunnel lining, all the rings "break joint," with the exception of those at the bore segments, as will be described later.

    This type of iron, when the original type was modified, came to be known as the ordinary pocketless iron; that is, the weight is of the ordinary or lighter type, in contradistinction to the heavier one, which later supplanted it, and the caulking groove runs along the edges of the flanges and does not form pockets around the bolt holes, as did the groove in a later type.

    Each ring is made up of eleven segments and a key piece. Of these, nine have radial joints at both ends, and are called "A" segments; two, called "B" segments, have a radial joint at one end and a non-radial joint at the other. The non-radial joint is placed next to the key, which is 12.25 in. wide at the outside circumference of the iron and 12.50 in. wide at the inside.

    The web is not of uniform thickness. The middle part of each A and B segment is 1½ in. thick; at the distance of 6 in. from the root of each flange, the thickness of web begins to increase, so that at the root it is 2-3/8 in. thick. The web of the key plate is 1¾ in. thick.

    The bolts are of mild steel, and are 1½ in. in diameter; there are 67 in one circumferential joint and 5 in each radial joint. As there are 12 such radial joints, there are altogether 60 bolts in the cross-joints, making a total of 127 bolts per ring.

    This original type of ordinary iron was modified for a special purpose as follows: It was known that for some distance on either side of the river, and especially at Weehawken, the tunnels would pass through a gravel formation, rather open, and containing a heavy head of water. It was thought that, by carrying the caulking groove around the bolt holes, it would be possible to make them more water-proof than by the simple use of the red-leaded grummets. Hence the "Pocket Iron" was adopted for this situation, the name being derived from the pocket-like recess which the caulking groove formed when extended around the bolt hole. The details of this lining are shown on Fig.

    11, and the iron (except for the pockets) is exactly like the pocketless type.

    [Illustration: DETAILS OF ALL TYPES OF METAL LININGS USED IN SUBAQUEOUS SHIELD-DRIVEN TUNNELS FIG. 11.]

    On the New York side, in both North and South Tunnels, two short lengths were built with cast-steel lining. This was done where unusual stresses were expected to come on the lining, namely, at the point where the invert passed from firm ground to soft, and also where the tunnels passed under the heavy river bulkhead wall.

    The design was precisely the same as for the ordinary pocketless iron, and Fig. 11 shows the details. After the tunnels had entered into the actual under-river portion, several phenomena (which will be described later) led to the fear that the tunnels, being lighter than the semi-liquid mud they displaced, might be subject to a buoyant action, and therefore a heavier type of lining was designed. The length of ring, number of bolts, etc., were just the same as for the lighter iron, but the thickness of the web was increased from 1½ to 2 in., the thickness of the flanges was proportionately increased, and the diameter of the bolts was increased from 1½ to 1¾ in.

    This iron was all of the pocketless type, shown in Fig. 11. Table 18 gives the weights of the various types of lining.

    TABLE 18.--WEIGHTS OF TUNNEL LINING, DIAMETER AND WEIGHTS OF BOLTS, ETC.

    +=========+===============+========+========+=======+========+========| |Reference|Type of Lining.| Weight | Weight |Weight | Weight |Diameter| |No. | | of one | of one |of one | of one | of | | | | "A" | "B" |key, in|complete| bolts, | | | |Segment,|Segment,|pounds.|ring, in| in | | | | in | in | |pounds. |inches. | | | |pounds. |pounds. | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |---------+---------------+--------+--------+-------+--------+--------| |1 |Ordinary cast | 2,063 | 2,068 | 480 | 23,183 | 1½ | | |iron without | | | | | | | |caulking | | | | | | | |pockets. | | | | | | |2 |Ordinary cast | 2,038 | 2,043 | 469 | 22,897 | 1½ | | |iron with | | | | | | | |caulking | | | | | | | |pockets. | | | | | | |3 |Ordinary cast | 2,247 | 2,252 | 522 | 25,249 | 1½ | | |steel without | | | | | | | |caulking | | | | | | | |pockets. | | | | | | |4 |Heavy cast iron| 2,579 | 2,584 | 606 | 28,985 | 1¾ | | |without | | | | | | | |caulking | | | | | | | |pockets. | | | | | | +---------+---------------+--------+--------+-------+--------+--------+

    +=========+===============+========+=======+=========+ |Reference|Type of Lining.| Weight |Weight | Total | |No. | | of 1 | of |weight of| | | | bolt, |bolts, |one ring | | | |nut, and| nuts, |(segments| | | | 2 | and | and | | | |washers,|washers| bolts), | | | | in | per | in | | | |pounds. | ring, | pounds. | | | | | in | | | | | |pounds.| | |---------+---------------+--------+-------+---------| |1 |Ordinary cast | 6.62 | 840.7 | 24,024 | | |iron without | | | | | |caulking | | | | | |pockets. | | | | |2 |Ordinary cast | 6.62 | 840.7 | 23,738 | | |iron with | | | | | |caulking | | | | | |pockets. | | | | |3 |Ordinary cast | 6.62 | 840.7 | 26,090 | | |steel without | | | | | |caulking | | | | | |pockets. | | | | |4 |Heavy cast iron| 10.50 |1,333.5| 30,319 | | |without | | | | | |caulking | | | | | |pockets. | | | | +---------+---------------+--------+-------+---------+

    WEIGHTS OF VARIOUS TYPES OF LINING PER LINEAR FOOT OF TUNNEL.

    +---------+---------------+--------------+-------------+---------------+ |Reference|Type of Lining.|Weights of |Weights of |Weights of | |No. | |complete rings|bolts, nuts, |segments and | | | |(segments |and washers, |bolts in tunnel| | | |only), in |in pounds. |complete, in | | | |pounds. | |pounds. | |---------+---------------+--------------+-------------+---------------| |1 |Ordinary cast | 9,273.0 | 336.3 | 9,609.6 | | |iron without | | | | | |pockets. | | | | | | | | | | |2 |Ordinary cast | 9,158.8 | 336.3 | 9,495.2 | | |iron with | | | | | |pockets. | | | | | | | | | | |3 |Ordinary cast | 10,099.6 | 336.3 | 10,436.0 | | |steel without | | | | | |pockets. | | | | | | | | | | |4 |Heavy cast iron| 11,594.0 | 533.4 | 12,127.6 | | |without | | | | | |pockets. | | | | +=========+===============+==============+=============+===============+

    The weights in Table 18 are calculated by assuming cast iron to weigh 450 lb. per cu. ft., and cast steel 490 lb. In actual practice the "ordinary" iron was found to weigh a little more than the weights given, and the "heavy" a little less.

    The silt in the sub-river portion averaged about 100 lb. per cu. ft., so that the weight of the silt displaced by the tunnel was about 41,548 lb. per lin. ft.

    Taper Rings.--In order to pass around curves (whether horizontal or vertical), or to correct deviation from line or grade, taper rings were used; by this is meant rings which when in place in the tunnels were wider than the standard rings, either at one side (horizontal tapers or "Liners"), or at the top ("Depressors"), or at the bottom ("Elevators").

    In the original design a ½-in. taper was called for, that is, the wide side of the ring was ½ in. wider than the narrow side, which was of the standard width of 2 ft. 6 in. As a matter of fact, during construction, not only ½-in., but ¾-in. and 1-in. tapers were often used.

    These taper rings necessitated each plate having its own unalterable position in the ring, hence each plate of the taper ring was numbered, so that no mistake could be made during erection.

    The taper rings were made by casting a ring with one circumferential flange much thicker than usual, and then machining off this flange to the taper. This was not only much cheaper than making a special pattern for each plate, but made it possible to see clearly where and what tapers were used in the tunnel.

    Taper rings were provided for all kinds of lining (except the cast steel), and the lack of taper steel rings was felt when building the steel-lined parts of the tunnel, as nothing could be done to remedy deviations from line or grade until the steel section was over and cast iron could again be used. Table 19 gives the weights of the different kinds of tapers used.

    TABLE 19.--WEIGHTS OF CAST-IRON TAPER RINGS, IN POUNDS PER COMPLETE

    RING.

    +

    Classification. |Weight of cast iron per complete ring,
    | in pounds.
    ---------------------------------+--------------------------------------
    Ordinary pocketless ½- in. taper| 23,767.7
    " " 1- " " | 24,352.4
    " pocket ½- " " | 23,481.7
    Heavy pocketless ½- in. taper | 29,564.8
    " " ¾- " " | 29,854.7
    " " 1- " " | 30,144.6
    =================================+=======================================

    Cast-Steel Bore Segments and Accessories.--The following feature of these tunnels is different from any hitherto built. It was the original intention to carry the rolling load independent of the tunnel, or to assist the support of the silt portion of the structure by a single row of screw-piles, under each tunnel, and extending down to firmer ground than that through which the tunnels were driven. Therefore, provision had to be made whereby these piles could be put down through the invert of the tunnel with no exposure of the ground.

    [Illustration: DETAILS OF BORE SEGMENTS AND ACCESSORIES USED IN SUBAQUEOUS SHIELD DRIVEN TUNNELS FIG. 12.]

    This provision was afforded by the "Bore Segments," which are shown in detail in Fig. 12. There are two segments, called No. 1 and No. 2, respectively. These two segments are bolted together in the bottom of two adjacent rings, and thus form a "Pile Bore." As the piles were to be kept at 15-ft. centers, and as the tunnel rings were 2 ft. 6 in. in length, it will be seen that, between each pair of bore-segment rings, there came four "Plain" rings. The plain rings were built up so that the radial joints broke joint from ring to ring, but with the bore-segment rings this could not be done, without unnecessarily adding to the types of segments.

    The bore segments were made of cast steel, and were quite complicated castings, the principle, however, was quite simple. The segments provided an opening just a little larger than the shaft of the pile, the orifice being 2 ft. 7 in. in diameter at the smallest (lowest) point, while the shaft of the pile was to be 2 ft. 5¼ in. In order to allow of the entry of the screw-blade or helix of the pile, a slot was formed in the depth of Bore Segment No. 1, so that, when a pile was put in position above the bore, the blade, when revolved, would enter the slot and thus pass under the metal lining, although the actual orifice was only slightly larger than the pile shaft.

    The wall of the pile orifice in Segment No. 2 was made lower than that in No. 1 so as to allow the blade to enter the slot in Segment No. 1.

    When the pile is not actually in process of being sunk, this lower height in No. 2 is made up with the removable "distance piece." This had a tongue at one end which engaged in a recess cast to take it in Segment No. 2 and was held in place by a key piece at the other end of the distance piece. Details of the distance piece and key are shown in Fig. 12.

    The flanges around the pile bore were made flat and furnished with twelve tapped holes, six in Segment No. 1 and six in Segment No. 2, for the purpose of attaching the permanent arrangements in conjunction with which the pile was to be attached to the track system, independently of the tunnel shell, or directly to the tunnel. It was never decided which of these alternatives would be used, for, before this decision was reached, it was agreed that, at any rate for the present, it was better not to put down piles at all.

    To close the bore, the "Bore Plug" was used. This is shown on Fig. 12.

    It was of cast steel, and was intended to act as a permanent point of the screw-pile, that is, the blade section was to be attached to the bore plug, the distance piece and key were to be removed, and the pile was to be rotated until the blade had cleared the slot; the distance piece and key were then to be replaced and sinking resumed.

    The plug was held in place against the pressure of the silt by the two "dogs," while the dogs themselves were attached to the tunnel, as shown in Fig. 12. The ends of the dogs, which rested on the flanges of the metal lining of the tunnel, were prevented from being knocked off the flanges (and thus releasing the plug) by steel clips.

    It was expected that it might be desirable to keep the lower end of the piles open during their sinking, so that the bore plugs were not made permanently closed, but a seating was formed on the inner circumference of the plug, and on the seating was placed the "Plug Cover," made of cast iron, 18¾ in. in diameter and 3 in. thick, furnished with a lug for lifting and a 3-in. tapped hole closed by a screw-plug, through which any soundings or samples of ground could be taken prior to sinking the piles.

    This plug cover was held in place by a heavy steel "Yoke" under it, which engaged on the under side of the flange, on top of which the cover was set. The yoke was attached to the cover by a 1¾-in. tap-bolt, screwed into the yoke and passing through a 2-in. hole bored in the center of the cover. This rather peculiar mode of attaching the cover was adopted so that the cover could be removed by taking off the nut of the yoke, in case it was desired to open the end of the pile during the process of sinking.

    The plug was a fairly close fit at the bottom of the orifice, that is, at the outside circumference of the tunnel, where the bore was 2 ft. 7 in. in diameter and the plug 2 ft. 6¾ in., but at the top of the bore-segment there was more clearance, as the plug was cylindrical while the bore tapered outward. To fill this space, it was intended that steel wedges should be used while the shield was being driven, so that they would withstand the crushing action of the thrusting shield, and, when the shield was far enough ahead, that they should be removed and replaced by hardwood wedges.

    This method was only used in the early weeks of the work; the modification of not using the shield-jacks which thrust against the bore segments was then introduced, and the wooden wedges were put in, when the bore plugs were set in place, and driven down to the stage of splitting.

    When it was resolved not to sink the screw-piles, the bores had to be closed before putting in the concrete lining. This was done by means of the covers shown in Fig. 13. The bore plug and all its attachments were removed, and the flat steel cover, 2 in. thick and with stiffening webs on the under side, was placed over the circular flanges of the pile bore. The cover was attached to the bore segments by twelve 1½-in. stud-bolts, 6 in. long, in the bolt holes already mentioned as provided on these flanges.

    When these were in place, with lead grummets under the heads of the bolts, and the grooves caulked, the bore segments were water-tight, except in Bore Segment No. 2, at the joint of the distance piece; and, to keep water from entering here, this segment was filled to the level of the top of the flanges with 1:1 Portland cement mortar.

    [Illustration: SUBAQUEOUS TUNNELS COVER FOR BORE SEGMENTS FIG. 13.]

    The weights of the various parts of the bore segments are given in Table 20.

    TABLE 20.--WEIGHTS OF BORE SEGMENTS AND ACCESSORIES, IN POUNDS.

    +=====+

    Part. | No. | Material. | Weight, in pounds.
    --------------------+-----+---------------+--------------------
    Bore Segment No. 1 | 1 | Cast Steel | 3,004.0
    Bore Segment No.

    2 | 1 | " " | 2,628.0
    Distance piece | 1 | " " | 423.5
    Key | 1 | " " | 34.3
    Plug | 1 | " " | 1,192.5
    Yoke | 1 | " " | 57.3
    Dogs | 2 | " " | 106.0
    Slot cover | 1 | Rolled steel | 6.4
    Plug cover | 1 | Cast iron | 162.0
    Dog holders | 2 | Rolled steel | 6.4
    --------------------+-----+---------------+--------------------
    Complete weight of one pair, without bolts| 7,620.4
    ==========================================+====================

    Sump Segments.--In order to provide sumps to collect the drainage and leakage water in the subaqueous tunnels, special "sump segments" were installed in each tunnel at the lowest point--about Station 241 + 00.

    The details of the design are shown in Fig. 14. The segment was built into the tunnel invert as though it were an ordinary "A" segment. In building the sump, three lining castings were bolted, one on top of the other, and attached to the flat upper surface of the sump segment; meanwhile, the bolts attaching the sump segment to the adjacent tunnel plates were taken out and the plate and lining segments were forced through the soft mud by hydraulic jacks, the three 6-in. holes in the bottom of the sump segment being opened in order to minimize the resistance. The sump when built appeared as shown in Fig. 14, the top connection being made with a special casting, as shown.

    The capacity of each sump is 500 gal., which is about the quantity of water entering the whole length of each subaqueous tunnel in 24 hours.

    Cross-Passages.--When the contract was let, provision was made for cross-passages between the tubular tunnels, in the form of special castings to be built into the tunnel lining at intervals. However, the idea was given up, and these castings were not made.

    Later, however, after tunnel building had started, the question was raised again, and it was thought that such cross-connections would be very useful to the maintenance forces, that it might be possible to build them safely, and that their subsequent construction would be made much easier if some provision were made for them while the shields were being driven.

    It was therefore arranged to build, at intervals of about 300 ft., two consecutive rings in each tunnel, at the same station in each tunnel, with their longitudinal flanges together, instead of breaking joint, as was usually done. The keys of these rings were displaced twelve bolt holes from their normal positions toward the other tunnel. This brought the keys about 6 ft. above the bench, so that if they were removed, together with the B plates below them, an opening of about 5 by 7 ft. would be left in a convenient position with regard to the bench.

    [Illustration: DETAILS OF SUMPS IN SUBAQUEOUS TUNNELS AT STATION 241 FIG. 14.]

    Nothing more was done until after the tunnels were driven. It was then decided to limit the cross-passages between the tubular tunnels to the landward side of the bulkhead walls. They were arranged as follows: three on the New York side, at Stations 203 + 22, 206 + 80, and 209 + 80, and two on the New Jersey side, at Stations 255 + 46 and 260 + 14.

    The cross-passages are square in cross-section.

    TABLE 21.--WEIGHTS OF SUMP SEGMENTS.

    +=====+===============+

    Part. | No. | Material. | Weight, in pounds.
    --------------------+-----+---------------+--------------------
    Middle top casting | 1 | Cast steel | 880
    End top castings | 2 | " " | 1,718
    Lining castings | 3 | " " | 18,232
    Sump segment | 1 | Cast iron | 3,560
    --------------------+-----+---------------+--------------------
    Total weight per sump, exclusive of bolts | 24,390
    ## +

    Turnbuckle Reinforcement for Cast-Iron Segments.--During the period of construction, a certain number of cast-iron segments, mostly in the roof, but in some cases at Manhattan in the invert, behind the river lines, became cracked owing to uneven pressures of the ground. Before the concrete lining was put in, considerable discussion occurred as to the wisest course to pursue with regard to these broken plates. It was finally thought best not to take the plates out, as more harm than good might be done, but to reinforce them with turnbuckles, as shown in Fig.

    1. The number of broken segments was distributed as follows:

    North Manhattan Tunnel 87, chiefly in silt (not under the river),
    South Manhattan Tunnel 7, chiefly in silt ( " " " " ),
    North Weehawken Tunnel 24, chiefly in sand ( " " " " ),
    South Weehawken Tunnel 48, chiefly in silt, under the Fowler
    Warehouse.

    The chief features of the tunnel lining have now been described, and, before giving any account of the methods of work, it will be well to mention briefly the salient features of the concrete lining which is placed within the actual lining.

    Design of Concrete Lining.

    This concrete lining will be considered and described in the following order:

    The New York Shield Chambers,

    Standard Cross-Section of Concrete Lining of Shield-Driven
    Tunnels,

    Final Lines and Grades, and How Obtained,

    Steel Rod Reinforcement of Concrete,

    Cross-Passage Lining,

    Special Provision for Surveys and Observations.

    [Illustration: SUBAQUEOUS TUNNELS TURNBUCKLES AND RODS REINFORCING TUNNEL SEGMENTS FIG. 15.]

    The New York Shield Chambers.--The cross-section of the concrete lining of these chambers is shown by Plate XXXII, referred to in the Land Tunnel Section. They are of the twin-tunnel double-bench type. The deep space beneath the floor is used as a sump for drainage, and manholes for access to the cable conduits are placed in the benches.

    [Illustration: TYPES OF CONCRETE LINING OF SHIELD-DRIVEN TUNNELS. FIG. 16.]

    Standard Cross-Section of Concrete Lining of Shield-Driven Tunnels.--The cross-section of the concrete lining of the tube tunnel is shown in Fig. 16. There are two main types, one extending from the shield chambers to the first bore segment, that is, to where the tunnel leaves solid ground and passes into silt, and the other which extends the rest of the way. The first type has a drain in the invert, the second has not.

    The height from the top of the rail to the soffit of the arch being less than 16 ft. 11 in., overhead pockets for the suspension of electrical conductors were set in the concrete arch on the vertical axis line at 10-ft. centers. These pockets are shown in Fig. 16. The benches are utilized for the cable conduits in the usual way. Ladders are provided on one side at 25-ft. and on the other side at 50-ft. intervals, to give access from the track level to the top of the benches. Refuge niches for trackmen are placed at 25-ft. intervals on the single-way conduits side only, as there is not enough room in front of the 4-way ducts.

    Manholes for giving access to the cable conduits, both power, and telephone and telegraph, are at 400-ft. intervals.

    Final Lines and Grades, and How Obtained.--It may be well to explain here how the final lines and grades for the track, and therefore for the concrete lining, were obtained and determined. It is first to be premised that the standard cross-section of the tunnel (that is, of the concrete and iron lining combined) is not maintained throughout the tunnel.

    In other words, the metal lining is of course uniform, or practically so, throughout; the interior surface of the concrete lining is also uniform from end to end, but the metal lining, owing to the difficulty of keeping the shields, and hence the tunnels built within them, exactly on the true line and grade, is not on such lines and grades; the concrete lining is built exactly on the pre-arranged lines and grades, consequently, the relative positions of the concrete and metal linings vary continually along the length of the structure, according to whether the metal lining is higher or lower than it should be, further to the north or to the south, or any combination of these.

    As before stated, it was strongly desired to encroach as little as possible on the standard 2-ft. concrete arch, and after some discussion it was decided that a thickness of 1 ft. 6 in. was the thinnest it was advisable to allow. This made it possible to permit the metal lining of the tunnel to be 6 in. lower, in respect to the level of the track at any point, than the standard section shows, and also allowed the center line of the track to have an eccentricity of 6 in. either north or south of the center line of the tunnel. This only left to be settled the extent to which the metal lining might be higher in respect to the track than that shown on the standard section.

    This amount was governed by the desirability of keeping sufficient clearance between the top of the rail and the iron lining in the invert to admit of the attachment of pile foundations and all the accompanying girder-track system which would necessarily be caused by the use of piles, should it ever become apparent after operation was begun, that, after all, it was essential to have the tunnels supported in this way.

    Careful studies were made of the clearance necessary, and it was decided that 4 ft. 9 in. was the minimum allowable depth from the top of the rail to the outside of the iron at the bottom. This meant that the iron lining could be 3 in. higher, with respect to the track level, than that shown on the standard section.

    All the determining factors for fixing the best possible lines and grades for the track within the completed metal lining were now at hand.

    In March, 1908, careful surveys of plan and elevation were made of the tunnels at intervals of 25 ft. throughout. The following operations were then performed to fix on the best lines and grades:

    First, for Line: It has been explained that the permissible deviation of the center line of the track on either side of the center line of the tunnel was 6 in. Had the metal lining been invariably of the true diameter, it would have been necessary to survey only one side of the tunnel; this would have given a line parallel to the center line, and might have been plotted as such; then, by setting off 6 in. on either side of this line, there would have been obtained a pair of parallel lines within which the center line of the track must lie. Owing to variations in the diameter of the tunnel, however, such a method was not permissible, and therefore the following process was used:

    When running the survey lines through the tunnel (which were the center lines used in driving the shields), offsets were taken to the inner edges of the flanges of the metal lining, both on the north and south sides, at axis level at each 25-ft. interval. On the plat on which the survey lines were laid down, and at each point surveyed, a distance was laid off to north and south equal to the following distances:

    Offset, as measured in the tunnel to north (or south), minus 10.08 ft.

    This 10.08 ft. (or 10 ft, 1 in.) represents 10 ft. 7 in., the true radius to inside of iron, minus 6 in., the permissible lateral deviation of the track from the axis of the tunnel.

    The result of this process was two lines, one on either side of the survey lines, not parallel to it or to each other, but approaching each other when the horizontal diameter was less than the true diameter, receding from each other when the diameter was more, and exactly 12 in. apart when the diameter was correct.

    As long as the center line of the track lay entirely within these two limiting lines, the condition that the concrete arch should not be 6 in. less in thickness than the standard 2 ft. was satisfied, and in order to arrive at the final line, the longest possible tangents that would be within these limits were adopted as the final lines; and, as the survey lines were those used in driving the tunnel shields (that is, the lines to which it was intended that the track should be built), the amount by which the new lines thus obtained deviated from the survey lines was a measure of the deviation of the finally adopted track and concrete line from the original contract lines.

    Next, for Grades: The considerations for grade were very similar to those for line. If the vertical diameter of the tunnel had been true at each 25-ft. interval surveyed, it would have been correct to plot the elevations of the crown (or invert) as a longitudinal section of the tunnel, and to have set up over those points others 6 in. above (as the metal lining could have been 6 in. lower than the standard section, which is equivalent to the track being an equal amount higher), and below these crown or invert elevations others 3 in. lower (as the metal lining could be 3 in. higher).

    Then, by joining the points 6 in. above in one line and those 3 in. below in another, there would have been obtained lines of limitation between which the track grades must lie. However, as the tunnel diameter was not uniformly correct, a modification of this method had to be made, as in the case of the line determination, the principle, however, remaining the same.

    The elevations were taken on the inner edges of the circumferential flanges of the metal lining, not only in the bottom, but also in the top, of the tunnel, at each 25-ft. interval; then, for the upper limit of the track at each such interval the following was plotted:

    Elevation of inner edge of flange at top, minus 16.58 ft.

    This 16.58 ft. (or 16 ft. 7 in.) was obtained thus: The standard height from the top of the rail to the inner edge of the iron flange is 17 ft. 1 in., but, as the track may be 6 in. above the standard or normal, the minimum height permissible is 16 ft. 7 in. For the lower limit of track at each 25-ft. interval the following was plotted:

    Elevation of inner edge of flange at bottom, plus 3.83 ft.

    This 3.83 ft. (or 3 ft. 10 in.) was obtained thus: The standard height from the top of the rail to the inner edge of the iron flange is 4 ft. 1 in. (5 ft. to outside of iron, less 11 in. for depth of flange), but, as the track may be 3 in. below the standard, the minimum height permissible is 4 ft, 1 in. less 3 in., or 3 ft. 10 in.

    By plotting the elevations thus obtained, two lines were obtained which were not parallel but were closer together or further apart according as the actual vertical diameter was less or greater than the standard, and the track grade had to lie within these two lines in order to comply with the requirements indicated above. The results of these operations for the North Tunnel are shown on Plate XXXVI.

    The greatest deviations between the lines and grades in the subaqueous tunnels as determined by these means and those as originally laid out in the contract drawings are on the Weehawken side, and were caused by the unexpected behavior of the tunnel when the shields were driven "blind" into the silt, causing a rise which could not be overcome, and the thrusting aside of one tunnel by the passage of the neighboring one. Had this unfortunate incident not occurred, it is clear that it would have been possible to adhere very closely indeed to the contract lines and grades, although the deviation is small, considering all things.

    The internal outline of the concrete cross-section is uniform throughout, and is built on the lines and grades thus described.

    Steel Rod Reinforcement of Concrete.--The original intention had been to line the metal lining of the tube tunnels with plain concrete, but, as the discussion on the foundation question continued, it was felt advisable, while still it was intended to put in the foundations, to guard against any stresses which were likely to come on the structure, by using a system of steel rods embedded circumferentially within the concrete. Designs were made on this basis, and even the necessary material prepared, before the decision to omit the piles altogether was reached.

    However, in order to provide a safeguard for the structure where it is partly or wholly beyond the solid rock, it was decided to use reinforcement, even with the piles omitted.

    For this purpose the tunnel was considered as a girder, and longitudinal reinforcement was provided at the top and bottom. The top reinforcement extends from a point 25 ft. behind the point where the crown of the tunnel passes out of rock on the New York side to where the crown passes into rock on the New Jersey side. The bottom reinforcement extends from where the invert of the tunnel passes out of rock on the New York side to where it passes into rock on the New Jersey side.

    The reinforcement both at top and bottom consists of twenty 1-in. square twisted rods, ten placed symmetrically on either side of the vertical axis, 9 in. apart from center to center and set 4 in. (to their centers) back from the face of the concrete.

    As a further precaution, circumferentially-placed rods were used on the landward side of the river lines, mainly to assist in preventing the distortion of shape which might occur here, either under present conditions, such as under the Fowler Warehouse at Weehawken, or under any possible different future conditions, such as might be brought about by building some new structure in the vicinity of the tunnels.

    For purposes of classification of the circumferential reinforcement, the tunnel was divided into two types, "B" and "C"; (Type "A" covering the portion which, being wholly in solid rock, was not reinforced at all).

    Type "B" covers the part of the tunnels on both sides of the river lying between the point where the top of the tunnel passes out of rock and the point where the invert passes out of rock on the Manhattan side, or out of gravel on the Weehawken side. The reinforcement consists of twenty 1-in. square longitudinal rods in the crown of the tunnel, as described for the general longitudinal reinforcement, together with 1-in. square circumferential rods at 10-in. centers, and extending over the arch to 2 ft. 3 in. below the horizontal axis.

    Type "C" extends from the latter limit of Type "B" to the river line on each side, and consists of longitudinal reinforcement in both top and bottom, as described before, together with circumferential reinforcement entirely around the tunnel, and formed of 1-in. square twisted rods at 15-in. centers.

    Type "D" consists of longitudinal reinforcement only, and extends from river line to river line, thus occupying 72.5% of the length in which concrete is used. The reinforcement consists of twenty 1-in. twisted rods at 9-in. centers in the crown, and twenty 1-in. rods at 9-in. centers in the invert. In addition to the three standard types, "B," "C," and "D," there were two sub-types which were used in Type "D," and in conjunction with it wherever the thickness of the center of the concrete arch became less than 1 ft.

    6 in., measuring to the outside of the metal lining. This thickness was one of the limits used in laying out the lines and grades, and in general the arch was not less than this. There were one or two short lengths, however, where it was less, for, if the arch thickness requirement had been adhered to, it would have resulted in a break of line or grade for the sake of perhaps only a few feet of thin arch, and it was here that the sub-types came into play.

    Sub-type 1 was used where the arch was less than 1 ft. 6 in. thick at the top. The extra reinforcement here consisted of 1-in. square twisted rods, 16 ft. long, laid circumferentially in the crown at 10-in. centers.

    Sub-type 2 was used where the arch was less than 1 ft. 6 in. thick at the side. The extra reinforcement here consisted of 1-in. square twisted rods, 16 ft. long, laid circumferentially, at the side on which the concrete was thin, at 10-in. centers. Very little of either of these two sub-types was used. The entire scheme is shown graphically and clearly on Plate XXXVII.

    Cross-Passage Lining.--There are two main types of cross-passages:

    Lined with steel plates, and unlined.

    There is only one example of lining with steel plates, namely, the most western one at Weehawken. This is built in rock which carried so much water that, in order to keep the tunnels and the passage dry, it was decided to build a concrete-lined passage, without attempting to stop the flow of water, and within this to place a riveted steel lining, not in contact with the concrete, but with a space between the two. This space was drained and the water led back to the shield chamber and thence to the Weehawken Shaft sump. The interior of the steel lining is covered with concrete.

    In the passages not lined with steel plates the square concrete lining is rendered on the inside with a water-proof plaster. Each of the passages is provided with a steel door.

    Provisions in Concrete Lining for Surveys and Observations.--The long protracted discussion as to the provision for foundations in these tunnels led to many surveys, tests, and observations, which were carried out during the constructive period, and, as it was desired to continue as many of these observations as possible up to and after the time when traffic started, certain provisions were made in the concrete lining whereby these requirements might be fulfilled. The chief points on which information was desired were as follows:

    The change in elevation of the tunnel,
    The change in lateral position of the tunnel,
    The change in shape of the tunnel,
    The tidal oscillation of the tunnel.

    A detailed account of these observations will be found in another paper on this work, but it may be said now that it was very desirable to be able to get this information independently of the traffic as far as possible, and therefore provision was made for carrying on the observations from the side benches.

    For studying the changes in level of the tunnel, a permanent bench-mark is established in each tunnel where it is in the solid rock and therefore not subject to changes of elevation; throughout the tunnel, brass studs are set in the bench at intervals of about 300 ft. A series of levels is run every month from the stable bench-mark on each of these brass plugs, thus obtaining an indication of the change of elevation that the tunnels have undergone during the month.

    These results are checked on permanent bench-marks in the subaqueous portion of the tunnels. These consist of rods, encased in pipes of larger diameter, which extend down through the tunnel invert into the bed-rock below the tunnel. Leakage is kept out by a stuffing-box in the invert. By measuring between a point on these rods where they pass through the invert and the tunnel itself a direct reading of the change of elevation of the tunnel is obtained.

    These measurements are taken at weekly intervals, and, as the tunnels are subject to tidal influences, being lower at high tide than at low tide, are always taken under the same conditions as to height of water in the river. These permanent bench-marks are at Stations 209 + 05 and 256 + 02 (about 100 ft. on the shoreward side of the river line in each case) in the South Tunnel, at Stations 220 + 00 and 243 + 86, also in the South Tunnel, and at Station 231 + 78 in the North Tunnel.

    In order to study the lateral change of position, a base line was established on the side bench at each end of each tunnel in the portion built through the solid rock.

    At intervals of about 300 ft. throughout each tunnel, alignment pockets are formed in the concrete arch, also above the bench, on the south bench of the North Tunnel and the north bench of the South Tunnel. In each pocket is placed a graduated and verniered brass bar, so that, when the base line is projected on these bars, the lateral movement of the tunnel can be read directly. As it was desirable to have as much cross-connection as possible between the tunnels at the points where the instruments were to be set up, five of the main survey stations were set opposite each of the five cross-passages.

    Then, for the purpose of increasing the cross-connection still further, pipes 6 in. in diameter were put through from one tunnel to the other at axis level at Stations 220 + 60, 231 + 78, 234 + 64, 241 + 99, and 251 + 13, and a survey station was put in opposite each one.

    Points were established at Station 220 + 00, which is the point of intersection for the curve on the original center line of the tunnel, and also at Station 220 + 23, where the intersection of the track center line comes in the North Tunnel. As it was desirable to have the survey stations not much more than 300 ft. apart, so as to obtain clear sights, other stations were established so that the distances between survey stations were at about that interval.

    For studying changes of shape in the tunnel, brass "diameter markers" were inserted at each survey station in the concrete lining at the extremities of the vertical and horizontal axes. These were pieces of brass bar, 3/8 in. in diameter and 6 in. long, set in the concrete and projecting 5/8 in. into the tunnel, so that a tape could be easily held against the marker and read.

    For obtaining the tidal oscillation of elevation of the tunnel, recording gauges are attached to the invert of the tunnel at each of the five permanent bench-marks referred to above in such a way that the recording pencil of the gauge is actuated by the rod of the permanent bench-mark. A roll of graduated paper is driven by clock-work below the recording pencil which thus marks automatically the relative movement between the moving tunnel and the stable rods.

    These have shown that in the subaqueous part of the tunnel there is a regular tidal fluctuation of elevation, the tunnel moving down as the tide rises, and rising again when the tide falls. For an average tide of about 5 ft. the tunnel oscillation would be about 1/8 in. Before the concrete lining was placed, there was a tidal change in the shape of the tunnel, which flattened about 1/64 in. at high tide. After the concrete lining was placed, this distortion seemed to cease.

    The general design and plan of the work have been described, and before giving any account of the contractor's methods in carrying it out, Table 22, showing the chief quantities of work in the river tunnels, is presented.

    Methods of Construction.

    The following is an account of the methods used by the contractor in carrying out the plans which have already been described. First, it may be well to point out the sequence of events as they developed in this work. These events may be divided into six periods.

    1.--Excavation and Iron Lining: June, 1903, to
    November, 1906;

    2.--Caulking and grummeting the iron lining:
    November, 1906, to June, 1907;

    3.--Surveys, tests and observations: April, 1907, to
    April, 1908;

    4.--Building cross-passages and capping pile bores:
    April, 1908, to November, 1908;

    5.--Placing the concrete lining: November, 1908, to
    June, 1909;

    6.--Cleaning up and various small works: June, 1909,
    to November, 1909.

    The tunnels were under an average air pressure of 25 lb. per sq. in. above normal for all except Periods 5 and 6, during which times there was no air pressure in the tunnels.

    All the work will be described in this paper except that under Period 3 which will be found in another paper.

    Period 1.--Excavation and Iron Lining, June, 1903, to November, 1906.--Table 23 gives the chief dates in connection with this period.

    Manhattan Shield Chambers.--The Manhattan shield chamber construction will be first described. The Weehawken shield chambers have been described under the Land Tunnel Section, as they are of the regular masonry-lined Land Tunnels type, whereas the Manhattan chambers are of segmental iron lining with a concrete inner lining.

    During the progress of excavation, the location of the New York shield chambers was moved back 133 ft., as previously described in the "Land Tunnel" Section, and when the location had been finally decided, there was a middle top heading driven all through the length now occupied by the shield chamber. Narrow cross-drifts were taken out at right angles to the top heading, and from the ends of these the wall-plate headings were taken out. Heavy timbering was used, as the rock cover was only about 6 ft., and the whole span to be covered was 60 ft.

    The process adopted was to excavate and timber the north side first, place the iron lining, and then excavate the south side, using the iron of the north side as the supports for the north ends of the segmental timbering of the south. The only incident of note was that at 2:00 A.M., on October 20th, 1904, the rock at the west end of the south wall-plate heading was pierced. Water soon flooded the

    Edition notice Project Gutenberg source, credits & licence

    The reading text above is the public-domain work. The Project Gutenberg header, production credits and licence are kept here as provenance rather than shown before the book.

    Title
    Transactions of the American Society of Civil Engineers, Vol. LXVIII, Sept. 1910
    Author
    Bertram Henry Majendie Hewett
    Release date
    February 21, 2013 [eBook #42149]
    Language
    English
    Credits
    Produced by Juliet Sutherland, Martin Mayer and the Online
    Most recently updated
    October 23, 2024
    Front matter as received (title page, contents)
    [Transcribers' notes:
    
    Some tables don't sum to the numbers indicated; no corrections have been
    made. All numbers are from the original.
    
    Minor inconsistencies in hyphenation have been retained.
    
    Subscripts are represented by underscore and curly braces e.g., CO_{2}.
    
    Italics are represented by underscores before and after e.g., _italics_.
    
    Bold is represented by equal signs before and after e.g., =bold=.
    
    Small caps have been replaced with ALL CAPS.]
    
    
    
    
     AMERICAN SOCIETY OF CIVIL ENGINEERS
    
     INSTITUTED 1852
    
     TRANSACTIONS
    
     Paper No. 1155
    
     THE NEW YORK TUNNEL EXTENSION OF THE
     PENNSYLVANIA RAILROAD.
    
     THE NORTH RIVER TUNNELS.[A]
    
     BY B. H. M. HEWETT AND W. L. BROWN, MEMBERS, AM. SOC. C. E.
    
     [A] Presented at the meeting of June 1st, 1910.
    Header as received
    The Project Gutenberg eBook of Transactions of the American Society of Civil Engineers, Vol. LXVIII, Sept. 1910
        
    This eBook is for the use of anyone anywhere in the United States and
    most other parts of the world at no cost and with almost no restrictions
    whatsoever. You may copy it, give it away or re-use it under the terms
    of the Project Gutenberg License included with this eBook or online
    at www.gutenberg.org. If you are not located in the United States,
    you will have to check the laws of the country where you are located
    before using this eBook.
    
    Title: Transactions of the American Society of Civil Engineers, Vol. LXVIII, Sept. 1910
    
    Author: Bertram Henry Majendie Hewett
            W. L. Brown
    
    
            
    Release date: February 21, 2013 [eBook #42149]
                    Most recently updated: October 23, 2024
    
    Language: English
    
    Other information and formats: www.gutenberg.org/ebooks/42149
    
    Credits: Produced by Juliet Sutherland, Martin Mayer and the Online
            Distributed Proofreading Team at http://www.pgdp.net
    Full Project Gutenberg licence
        
    
    Updated editions will replace the previous one—the old editions will
    be renamed.
    
    Creating the works from print editions not protected by U.S. copyright
    law means that no one owns a United States copyright in these works,
    so the Foundation (and you!) can copy and distribute it in the United
    States without permission and without paying copyright
    royalties. Special rules, set forth in the General Terms of Use part
    of this license, apply to copying and distributing Project
    Gutenberg™ electronic works to protect the PROJECT GUTENBERG™
    concept and trademark. Project Gutenberg is a registered trademark,
    and may not be used if you charge for an eBook, except by following
    the terms of the trademark license, including paying royalties for use
    of the Project Gutenberg trademark. If you do not charge anything for
    copies of this eBook, complying with the trademark license is very
    easy. You may use this eBook for nearly any purpose such as creation
    of derivative works, reports, performances and research. Project
    Gutenberg eBooks may be modified and printed and given away—you may
    do practically ANYTHING in the United States with eBooks not protected
    by U.S. copyright law. Redistribution is subject to the trademark
    license, especially commercial redistribution.
    
    
    START: FULL LICENSE
    
    THE FULL PROJECT GUTENBERG™ LICENSE
    
    PLEASE READ THIS BEFORE YOU DISTRIBUTE OR USE THIS WORK
    
    To protect the Project Gutenberg™ mission of promoting the free
    distribution of electronic works, by using or distributing this work
    (or any other work associated in any way with the phrase “Project
    Gutenberg”), you agree to comply with all the terms of the Full
    Project Gutenberg License available with this file or online at
    www.gutenberg.org/license.
    
    Section 1. General Terms of Use and Redistributing Project Gutenberg
    electronic works
    
    1.A. By reading or using any part of this Project Gutenberg
    electronic work, you indicate that you have read, understand, agree to
    and accept all the terms of this license and intellectual property
    (trademark/copyright) agreement. If you do not agree to abide by all
    the terms of this agreement, you must cease using and return or
    destroy all copies of Project Gutenberg electronic works in your
    possession. If you paid a fee for obtaining a copy of or access to a
    Project Gutenberg electronic work and you do not agree to be bound
    by the terms of this agreement, you may obtain a refund from the person
    or entity to whom you paid the fee as set forth in paragraph 1.E.8.
    
    1.B. “Project Gutenberg” is a registered trademark. It may only be
    used on or associated in any way with an electronic work by people who
    agree to be bound by the terms of this agreement. There are a few
    things that you can do with most Project Gutenberg electronic works
    even without complying with the full terms of this agreement. See
    paragraph 1.C below. There are a lot of things you can do with Project
    Gutenberg electronic works if you follow the terms of this
    agreement and help preserve free future access to Project Gutenberg
    electronic works. See paragraph 1.E below.
    
    1.C. The Project Gutenberg Literary Archive Foundation (“the
    Foundation” or PGLAF), owns a compilation copyright in the collection
    of Project Gutenberg electronic works. Nearly all the individual
    works in the collection are in the public domain in the United
    States. If an individual work is unprotected by copyright law in the
    United States and you are located in the United States, we do not
    claim a right to prevent you from copying, distributing, performing,
    displaying or creating derivative works based on the work as long as
    all references to Project Gutenberg are removed. Of course, we hope
    that you will support the Project Gutenberg mission of promoting
    free access to electronic works by freely sharing Project Gutenberg
    works in compliance with the terms of this agreement for keeping the
    Project Gutenberg name associated with the work. You can easily
    comply with the terms of this agreement by keeping this work in the
    same format with its attached full Project Gutenberg License when
    you share it without charge with others.
    
    1.D. The copyright laws of the place where you are located also govern
    what you can do with this work. Copyright laws in most countries are
    in a constant state of change. If you are outside the United States,
    check the laws of your country in addition to the terms of this
    agreement before downloading, copying, displaying, performing,
    distributing or creating derivative works based on this work or any
    other Project Gutenberg work. The Foundation makes no
    representations concerning the copyright status of any work in any
    country other than the United States.
    
    1.E. Unless you have removed all references to Project Gutenberg:
    
    1.E.1. The following sentence, with active links to, or other
    immediate access to, the full Project Gutenberg License must appear
    prominently whenever any copy of a Project Gutenberg work (any work
    on which the phrase “Project Gutenberg” appears, or with which the
    phrase “Project Gutenberg” is associated) is accessed, displayed,
    performed, viewed, copied or distributed:
    
        This eBook is for the use of anyone anywhere in the United States and most
        other parts of the world at no cost and with almost no restrictions
        whatsoever. You may copy it, give it away or re-use it under the terms
        of the Project Gutenberg™ License included with this eBook or online
        at www.gutenberg.org. If you
        are not located in the United States, you will have to check the laws
        of the country where you are located before using this eBook.
      
    1.E.2. If an individual Project Gutenberg electronic work is
    derived from texts not protected by U.S. copyright law (does not
    contain a notice indicating that it is posted with permission of the
    copyright holder), the work can be copied and distributed to anyone in
    the United States without paying any fees or charges. If you are
    redistributing or providing access to a work with the phrase “Project
    Gutenberg” associated with or appearing on the work, you must comply
    either with the requirements of paragraphs 1.E.1 through 1.E.7 or
    obtain permission for the use of the work and the Project Gutenberg
    trademark as set forth in paragraphs 1.E.8 or 1.E.9.
    
    1.E.3. If an individual Project Gutenberg electronic work is posted
    with the permission of the copyright holder, your use and distribution
    must comply with both paragraphs 1.E.1 through 1.E.7 and any
    additional terms imposed by the copyright holder. Additional terms
    will be linked to the Project Gutenberg License for all works
    posted with the permission of the copyright holder found at the
    beginning of this work.
    
    1.E.4. Do not unlink or detach or remove the full Project Gutenberg
    License terms from this work, or any files containing a part of this
    work or any other work associated with Project Gutenberg.
    
    1.E.5. Do not copy, display, perform, distribute or redistribute this
    electronic work, or any part of this electronic work, without
    prominently displaying the sentence set forth in paragraph 1.E.1 with
    active links or immediate access to the full terms of the Project
    Gutenberg License.
    
    1.E.6. You may convert to and distribute this work in any binary,
    compressed, marked up, nonproprietary or proprietary form, including
    any word processing or hypertext form. However, if you provide access
    to or distribute copies of a Project Gutenberg work in a format
    other than “Plain Vanilla ASCII” or other format used in the official
    version posted on the official Project Gutenberg website
    (www.gutenberg.org), you must, at no additional cost, fee or expense
    to the user, provide a copy, a means of exporting a copy, or a means
    of obtaining a copy upon request, of the work in its original “Plain
    Vanilla ASCII” or other form. Any alternate format must include the
    full Project Gutenberg License as specified in paragraph 1.E.1.
    
    1.E.7. Do not charge a fee for access to, viewing, displaying,
    performing, copying or distributing any Project Gutenberg works
    unless you comply with paragraph 1.E.8 or 1.E.9.
    
    1.E.8. You may charge a reasonable fee for copies of or providing
    access to or distributing Project Gutenberg electronic works
    provided that:
    
        • You pay a royalty fee of 20% of the gross profits you derive from
            the use of Project Gutenberg works calculated using the method
            you already use to calculate your applicable taxes. The fee is owed
            to the owner of the Project Gutenberg trademark, but he has
            agreed to donate royalties under this paragraph to the Project
            Gutenberg Literary Archive Foundation. Royalty payments must be paid
            within 60 days following each date on which you prepare (or are
            legally required to prepare) your periodic tax returns. Royalty
            payments should be clearly marked as such and sent to the Project
            Gutenberg Literary Archive Foundation at the address specified in
            Section 4, “Information about donations to the Project Gutenberg
            Literary Archive Foundation.”
        
        • You provide a full refund of any money paid by a user who notifies
            you in writing (or by e-mail) within 30 days of receipt that s/he
            does not agree to the terms of the full Project Gutenberg™
            License. You must require such a user to return or destroy all
            copies of the works possessed in a physical medium and discontinue
            all use of and all access to other copies of Project Gutenberg™
            works.
        
        • You provide, in accordance with paragraph 1.F.3, a full refund of
            any money paid for a work or a replacement copy, if a defect in the
            electronic work is discovered and reported to you within 90 days of
            receipt of the work.
        
        • You comply with all other terms of this agreement for free
            distribution of Project Gutenberg™ works.
        
    
    1.E.9. If you wish to charge a fee or distribute a Project
    Gutenberg™ electronic work or group of works on different terms than
    are set forth in this agreement, you must obtain permission in writing
    from the Project Gutenberg Literary Archive Foundation, the manager of
    the Project Gutenberg™ trademark. Contact the Foundation as set
    forth in Section 3 below.
    
    1.F.
    
    1.F.1. Project Gutenberg volunteers and employees expend considerable
    effort to identify, do copyright research on, transcribe and proofread
    works not protected by U.S. copyright law in creating the Project
    Gutenberg™ collection. Despite these efforts, Project Gutenberg™
    electronic works, and the medium on which they may be stored, may
    contain “Defects,” such as, but not limited to, incomplete, inaccurate
    or corrupt data, transcription errors, a copyright or other
    intellectual property infringement, a defective or damaged disk or
    other medium, a computer virus, or computer codes that damage or
    cannot be read by your equipment.
    
    1.F.2. LIMITED WARRANTY, DISCLAIMER OF DAMAGES - Except for the “Right
    of Replacement or Refund” described in paragraph 1.F.3, the Project
    Gutenberg Literary Archive Foundation, the owner of the Project
    Gutenberg™ trademark, and any other party distributing a Project
    Gutenberg™ electronic work under this agreement, disclaim all
    liability to you for damages, costs and expenses, including legal
    fees. YOU AGREE THAT YOU HAVE NO REMEDIES FOR NEGLIGENCE, STRICT
    LIABILITY, BREACH OF WARRANTY OR BREACH OF CONTRACT EXCEPT THOSE
    PROVIDED IN PARAGRAPH 1.F.3. YOU AGREE THAT THE FOUNDATION, THE
    TRADEMARK OWNER, AND ANY DISTRIBUTOR UNDER THIS AGREEMENT WILL NOT BE
    LIABLE TO YOU FOR ACTUAL, DIRECT, INDIRECT, CONSEQUENTIAL, PUNITIVE OR
    INCIDENTAL DAMAGES EVEN IF YOU GIVE NOTICE OF THE POSSIBILITY OF SUCH
    DAMAGE.
    
    1.F.3. LIMITED RIGHT OF REPLACEMENT OR REFUND - If you discover a
    defect in this electronic work within 90 days of receiving it, you can
    receive a refund of the money (if any) you paid for it by sending a
    written explanation to the person you received the work from. If you
    received the work on a physical medium, you must return the medium
    with your written explanation. The person or entity that provided you
    with the defective work may elect to provide a replacement copy in
    lieu of a refund. If you received the work electronically, the person
    or entity providing it to you may choose to give you a second
    opportunity to receive the work electronically in lieu of a refund. If
    the second copy is also defective, you may demand a refund in writing
    without further opportunities to fix the problem.
    
    1.F.4. Except for the limited right of replacement or refund set forth
    in paragraph 1.F.3, this work is provided to you ‘AS-IS’, WITH NO
    OTHER WARRANTIES OF ANY KIND, EXPRESS OR IMPLIED, INCLUDING BUT NOT
    LIMITED TO WARRANTIES OF MERCHANTABILITY OR FITNESS FOR ANY PURPOSE.
    
    1.F.5. Some states do not allow disclaimers of certain implied
    warranties or the exclusion or limitation of certain types of
    damages. If any disclaimer or limitation set forth in this agreement
    violates the law of the state applicable to this agreement, the
    agreement shall be interpreted to make the maximum disclaimer or
    limitation permitted by the applicable state law. The invalidity or
    unenforceability of any provision of this agreement shall not void the
    remaining provisions.
    
    1.F.6. INDEMNITY - You agree to indemnify and hold the Foundation, the
    trademark owner, any agent or employee of the Foundation, anyone
    providing copies of Project Gutenberg™ electronic works in
    accordance with this agreement, and any volunteers associated with the
    production, promotion and distribution of Project Gutenberg™
    electronic works, harmless from all liability, costs and expenses,
    including legal fees, that arise directly or indirectly from any of
    the following which you do or cause to occur: (a) distribution of this
    or any Project Gutenberg work, (b) alteration, modification, or
    additions or deletions to any Project Gutenberg work, and (c) any
    Defect you cause.
    
    Section 2. Information about the Mission of Project Gutenberg
    
    Project Gutenberg is synonymous with the free distribution of
    electronic works in formats readable by the widest variety of
    computers including obsolete, old, middle-aged and new computers. It
    exists because of the efforts of hundreds of volunteers and donations
    from people in all walks of life.
    
    Volunteers and financial support to provide volunteers with the
    assistance they need are critical to reaching Project Gutenberg’s
    goals and ensuring that the Project Gutenberg collection will
    remain freely available for generations to come. In 2001, the Project
    Gutenberg Literary Archive Foundation was created to provide a secure
    and permanent future for Project Gutenberg and future
    generations. To learn more about the Project Gutenberg Literary
    Archive Foundation and how your efforts and donations can help, see
    Sections 3 and 4 and the Foundation information page at www.gutenberg.org.
    
    Section 3. Information about the Project Gutenberg Literary Archive Foundation
    
    The Project Gutenberg Literary Archive Foundation is a non-profit
    501(c)(3) educational corporation organized under the laws of the
    state of Mississippi and granted tax exempt status by the Internal
    Revenue Service. The Foundation’s EIN or federal tax identification
    number is 64-6221541. Contributions to the Project Gutenberg Literary
    Archive Foundation are tax deductible to the full extent permitted by
    U.S. federal laws and your state’s laws.
    
    The Foundation’s business office is located at 41 Watchung Plaza #516,
    Montclair NJ 07042, USA, +1 (862) 621-9288. Email contact links and up
    to date contact information can be found at the Foundation’s website
    and official page at www.gutenberg.org/contact
    
    Section 4. Information about Donations to the Project Gutenberg
    Literary Archive Foundation
    
    Project Gutenberg™ depends upon and cannot survive without widespread
    public support and donations to carry out its mission of
    increasing the number of public domain and licensed works that can be
    freely distributed in machine-readable form accessible by the widest
    array of equipment including outdated equipment. Many small donations
    ($1 to $5,000) are particularly important to maintaining tax exempt
    status with the IRS.
    
    The Foundation is committed to complying with the laws regulating
    charities and charitable donations in all 50 states of the United
    States. Compliance requirements are not uniform and it takes a
    considerable effort, much paperwork and many fees to meet and keep up
    with these requirements. We do not solicit donations in locations
    where we have not received written confirmation of compliance. To SEND
    DONATIONS or determine the status of compliance for any particular state
    visit www.gutenberg.org/donate.
    
    While we cannot and do not solicit contributions from states where we
    have not met the solicitation requirements, we know of no prohibition
    against accepting unsolicited donations from donors in such states who
    approach us with offers to donate.
    
    International donations are gratefully accepted, but we cannot make
    any statements concerning tax treatment of donations received from
    outside the United States. U.S. laws alone swamp our small staff.
    
    Please check the Project Gutenberg web pages for current donation
    methods and addresses. Donations are accepted in a number of other
    ways including checks, online payments and credit card donations. To
    donate, please visit: www.gutenberg.org/donate.
    
    Section 5. General Information About Project Gutenberg electronic works
    
    Professor Michael S. Hart was the originator of the Project
    Gutenberg concept of a library of electronic works that could be
    freely shared with anyone. For forty years, he produced and
    distributed Project Gutenberg eBooks with only a loose network of
    volunteer support.
    
    Project Gutenberg eBooks are often created from several printed
    editions, all of which are confirmed as not protected by copyright in
    the U.S. unless a copyright notice is included. Thus, we do not
    necessarily keep eBooks in compliance with any particular paper
    edition.
    
    Most people start at our website which has the main PG search
    facility: www.gutenberg.org.
    
    This website includes information about Project Gutenberg,
    including how to make donations to the Project Gutenberg Literary
    Archive Foundation, how to help produce our new eBooks, and how to
    subscribe to our email newsletter to hear about new eBooks.

    Source: Project Gutenberg ebook #42149. Public-domain status is recorded per item; the licence text above is reproduced unchanged.

    Source
    Project Gutenberg
    Record
    ebook 42149
    Rights
    public domain (US)
    Rendered
    2026-11-21
    Completeness
    First 200,000 characters rendered.